Wednesday, September 12, 2012

Latest Information On Roosevelt Island PS/IS 217 Construction Project From Principal Mandana Beckman

 Image of PS/IS 217 Construction Project

Commenting on the What's On Your Roosevelt Island Mind post, a Roosevelt Island resident wanted to know:
I'd like to know WHEN the work is going to be finished on the school (and what exactly are they doing to it) Getting real tired of all the lights they leave on overnight and over the weekend.
I asked PS/IS 217 Principal Mandana Beckman if she could provide an answer. Ms. Beckman replied:
I directed your question to our Custodial Engineer. Here was his response to the question posted.

The scope of the construction project is as follows :
  • 1) Replacing all roofs
  • 2) Flood elimination
  • 3) Replacing masonry as needed for elimination of leaks
  • 4) Replacing front facade of building
  • 5) Replacing front window only (Main Street side)
At the present time the masonry work is in my opinion 85% finished

roofing 50%

windows 95%

facade 75%

The work that is most disruptive ( lights, noise, etc. ) would be the roofing . It would be hard for me to give an accurate time of completion , due to factor such as weather, inspections, etc. If the weather holds and The Contractor uses his time wisely I still believe you are looking at November until the roof is complete and with it substantial noise and light reduction.
More information on PS/IS 217 is available at this post which includes a video of Ms. Mandana speaking to Roosevelt  Island parents about the school.

Tuesday, June 21, 2011

Masonry, Window and Roof Repairs At Roosevelt Island's PS/IS 217 Causing Health Hazard To Adjacent Building Residents - Breathing and Coughing Problems Develop From Construction Dust

Image of PS/IS 217 Under Renovation

 Jim Bates, Roosevelt Island Residents Association (RIRA) representative for 2-4 River Road and President of the Disabled Association reports:
... air pollution at 2-4 River Rd due to PS/IS 217 on going construction. Due to the dust and dirty screens, tenants are forced to keep windows shut and use our AC units causing high electrical bills.

Will the construction company pay for our electrical charges
Mr. Bates shares this message he sent to the offices of Assembly Member Micah Kellner and State Senator Jose Seranno, Manhattan Park representatives, RIOC and RIRA. From Mr. Bates:
For the past several weeks construction on the school adjacent to 2-4 River Rd has caused breathing and coughing problems for the tenants of 2-4 River Rd,

Our screens are grey from the dust and I am personally having breathing and coughing problems daily

I am asking for your help in seeing how this health hazard can be taken care of,

We need clean air for breathing, and closing our windows is not the answer, nor putting on our AC which draws outside air into our apartments and also cauises families higher electric rates

Last night I was up all night coughing and choking and spitting up phlegm

I thought I was having a asthma attach and gave my self a breathing treatment

This is serious

Please let me know if there is anything else I can do to remedy this health hazard
Responding to an earlier inquiry regarding the destruction of some Trees behind PS/IS 217, the school's Principal explained the reason for  the construction currently being undertaken:
The school was informed by the Department of Education that our school building would require extensive masonry work, along with window and roof repairs, and that this work would begin during the 2010-2011 school year. It was estimated that the project would last a minimum of two years, and would require that scaffolding be erected around the school’s perimeter.  This work has been mandated by the NYC Department of Buildings, and is completely out of the school’s control.  However, during both a formal meeting in November and an informal one in September, we received a complete overview of the project and relayed such information to all parties concerned, including custodial staff and the Living Library. We were given assurances at that time from the School Construction Authority that damage done as a result of the construction would be repaired by them, to our specifications. We are committed to ensuring that such restoration takes place, in partnership with the School Construction Authority and PS/IS 217 custodial staff.

Mandana Beckman
Principal
PS/IS 217