Friday, August 1, 2014

Report From RIOC President Charlene Indelicato - New Roosevelt Island Deputy Director Of Public Safety Lynda Marmara, NY State Citizen Emergency Preparedness Training, No Bids On New Tram Elevator, Cultural Center Renovations Completed by December 2014 , Blackwell Park Swing Tampering, Restriping Roads & Much More

Roosevelt Island Deputy Public Safety Director Lynda Marmara Via Strategic Planning And Security Services

Roosevelt Island Operating Corp (RIOC) President Charlene Indelicato sends the following report to the community.
This summer has been a very busy time on Roosevelt Island. Several capital projects have been completed: The Octagon Tennis Courts have been resurfaced, the Tram stations repainted, the entryway of the Good Shepherd Chapel restored, and the northern tip of Lighthouse Park has been reopened for public enjoyment. Many improvements to the Island are still in progress at locations such as the Tram stations, the Cultural Center and on all Island roads. In addition to construction projects, the Outdoor Summer Movie Series and other free public events continue to take place on the Island. For up-to-date information about these and other community notices, you may sign up for RIOC Advisories email alerts on our website: www.rioc.ny.gov.

New Deputy Director of Public Safety: Lynda Marmara

RIOC would like to extend a warm welcome to the newest member of our staff, Lynda Marmara. Marmara has joined us as the new Deputy Director of Public Safety and is well familiar with Roosevelt Island, having been assigned to the community in the past as a NYC police officer. She comes to us with decades of experience in police work and a strong background in emergency management. Marmara previously served as the Director of Public-Private Initiatives for the NYC Office of Emergency Management and most recently owned and led her own security company, Strategic Planning and Security Services, Inc. We are very pleased to have her on our team and look forward to her work on Roosevelt Island.

Citizen Preparedness Training

Next week, the NYS Office of Emergency Management (OEM) will be offering a free Citizen Preparedness training workshop. In addition to valuable information about how to prepare for natural or man-made disasters, each family participating will receive a free Citizen Preparedness Corps Response Starter Kit for attending. The kit includes a first aid kit, emergency food and water, AM/FM radio, flashlight, and more useful items.

The training will take place on August 6 at the Manhattan Park Theater Club (8 River Road) at 6 PM. While this session is free, participants must register in advance at  www.prepare.ny.gov/training-events in order to attend. We hope to see you there!

Outdoor Summer Movie Series

RIOC’s Outdoor Summer Movie Series (now located at Firefighter’s Field) continues on Saturday, August 9 with a screening of The Hobbit: Desolation of Smaug. Come out to the field at 7 p.m. for music, film trivia and night of movie fun under the stars. Food and drink will be available for purchase, bring a blanket or lawn chair. On Saturday, August 23rd, don't miss the final screening in the series, featuring the James Bond movie Goldfinger as well as a locally produced short A Necessary Music. This unique short film was shot on Roosevelt Island and features seventeen of our residents as actors. We hope to see you there!

Lighthouse Park

We are extremely pleased to be able to reopen the northern tip of Lighthouse Park for the community’s enjoyment. Contractors are currently completing a construction checklist and addressing a few final items to bring the project to completion, so expect to see workers in the vicinity of the park’s footbridges. While certain areas may be intermittently cordoned off to allow work to take place, the park area surrounding the Lighthouse will remain open to the public.

Cultural Center

Work on the Cultural Center at 504 Main Street has progressed. Demolition and removal of the water-damaged materials inside the Center was completed over the summer, and the floor fill has been poured to create a solid foundation. Contractors are currently re-framing the walls and performing electrical work. This project is scheduled to be completed in December 2014. We know how important the Cultural Center is to the community, and we look forward to reopening a new and improved space for public use.

Tram Elevators

Bids for the design and construction of new elevators at the Manhattan Tram Station were due last week on July 21; however, no proposals were submitted. This project is a very high priority for RIOC, and we are committed to finding a skilled contractor to carry out this important work. We will continue explore our options and will push to keep this project moving forward on schedule.

Re-Striping Roosevelt Island’s Roads

Over the past few weeks, the Island’s streets and Helix Ramp have been re-striped by contractors working with our Engineering department. Refreshing the paint job helps ensure that important street markings, especially at crosswalks and stop signs, are highly visible to both vehicles and pedestrians. Further re-striping work is scheduled to take place in the near future.

Blackwell Children’s Playground Swing

At the Blackwell Park Children’s Playground, a low toddler swing has repeatedly been tampered with. After repairs to the swing were made on July 7, the strap and related hardware were entirely removed from the area. RIOC will make repairs shortly and again restore the swing for young children to use. In the interest of safety, we ask that visitors to the park refrain from removing any hardware at the playground and contact us immediately to report any repairs that need to be made. If you have any information related to the play equipment’s disappearance, we encourage you to contact the Roosevelt Island Public Safety Department at 212-832-4545.

Tennis Permits

As a reminder, the newly resurfaced Octagon Tennis Courts are open for permit holders. If you would like to play, you may purchase a Tennis Permit online through the RIOC website – please visit us at rioc.ny.gov/tenniscourts.htm for more information or to apply.

Tram Inspection Service Changes

Leitner-Poma, operator of the Roosevelt Island Tramway, has advised that both Tram cabins are undergoing a comprehensive safety inspection. The tests began on Monday, July 28th and are scheduled to be completed by Friday, August 8th. One Tram cabin must be taken out of service during the inspection, requiring a change to its operating schedule. Please visit our website (rioc.ny.gov) for an updated operating schedule.

Sunday, September 23, 2012

Roosevelt Island Main Street Road Construction Safety Concerns From Resident and Response From RIOC


You Tube Video of Main Street Reconstruction Project

Roosevelt Island resident Raye Schwartz expresses concern over safety issues surrounding the Main Street Reconstruction Project and shares this message she sent to Roosevelt Island Operating Corp (RIOC) Public Safety Department Director Keith Guerra and Vice President of Operations Fernando Martinez last Friday.
This morning while I was baby sitting I needed to get something from Gristedes. I walked up Main Street past PS217 and found that I could not cross, so I turned around and walked south. I was going to use the crosswalk near Westview and The Child School, but found that I could not see the southbound traffic unless I actually walked into the street. That's because the line of sight was completely obstructed by huge trucks parked all the way from 217 and double parked at Westview.

I was not about to do that and endanger my grand daughter in her stroller. Further, there was so much traffic coming from the bridge that it was clear to me that even if I got across the street safely I would face another dangerous situation crossing at the bottom of the helix ramp.

I finally walked to the RIOC office and asked Carlina to notify you about this situation. FYI, there were two other people with strollers who were in the same predicament as well as an elderly wheelchair bound woman who was so frustrated that she was nearly in tears.

Further, this coming week is sure to be a nightmare because of bridge closings related to the UN general assembly meeting.

Based on these situations it is clear to me that there must be a public safety presence on foot at that area, not just periodic patrols in cars. That presence must be maintained throughout the repaving project. I am making this known to you because I fear that there can and possibly will be one or more serious accidents in that area without some kind of officer presence. Please do everything possible to make certain that pedestrians as well as school children are protected throughout this construction, that the lines of sight at crosswalks are not blocked, and some signage placed letting people know where they can cross safely.

Thanks in advance.
RIOC Director Margie Smith responded to Ms. Schwartz:
Thanks for the note. I’ll speak with Fernando and be sure there aren’t any unsafe conditions during the project work.
Mr. Guerra responded as well:
Thank you for the email. We at RIOC are trying to do the best we can under the circumstances. Street construction projects always pose issues, but rest assured that four different departments are working collectively to be on top of it. The Construction Company is mandated to have Flag-Personnel assisting with traffic flow during construction hours. Our Engineering and Transportation Departments are out there making sure they conform to the agreement. Our Community Relations Specialist is in constant contact with the administrators of P.S. 217 to remind folks about the traffic condition. The Public Safety Department is in the process of setting up a special detail, beginning Monday, to assist with traffic flow in front of P.S. 217 during morning drop-offs and afternoon pick-ups, as well as on Main Street. Hopefully, it will be better next week.

Regards,

KG

As an aside, our Officers on Patrol did observe two Delivery Trucks double-parked in front of Westview, and issued them summonses.
More on Main Street Reconstruction project from previous post.

Thursday, September 20, 2012

Roosevelt Island's River Road Closed Friday Thru Tuesday For Main Street Reconstruction Project - Bus Stop Moved To 40 River Road

Reported previously on the Main Street Reconstruction Project scheduled to last until March 2013.

Image of Main Street Reconstruction Project Beginning Today

Earlier today, the Roosevelt Island Operating Corp (RIOC) reported:
Please be advised River Road will be temporary closed from Friday, September 21st beginning at 8AM to Tuesday, September 25th at 5 PM due to the Main Street Reconstruction Project. During that time deliveries and pick-ups will only be allowed in the area. River Road will re-open on Wednesday, September 26th and will return to temporary construction closure times, 8AM to 5PM, for the duration of the Main Street Reconstruction Project.

As a result, the bus stop located at 10 River Road will be temporarily relocated to 40 River Road.

Wednesday, September 12, 2012

Update On Roosevelt Island Main Street Reconstruction Project - Gristedes/Motorgate Bus Stop Moved Across Street To 10 River Road

Image of Main Street Reconstruction Project Beginning Today

Reported yesterday that:
... on Wednesday, September 12, 2012 Main Street roadway reconstruction will commence from the area below the Helix ramp to 40 River Road. The scope of project will involve removal of the existing Z-Brick Pavers and installation of an asphalt surface....
The Roosevelt Island Operating Corp (RIOC) added today:
Due to the Main Street Reconstruction Project, the Motorgate/Gristedes Bus Stop has been temporary relocated to 10 River Road (On the South West Corner of Main Street and River Road).

Sincerely,

Roosevelt Island Operating Corp Advisories Group

Temporary Red Bus Stop At 10 River Road During Main Street Reconstruction Project

Below are some of the  Z Brick Pavers broken up and ready to be removed.

Image of Main Street Z Brick Pavers Being Broken Up and Removed

Tuesday, September 11, 2012

Roosevelt Island Main Street Road Reconstruction Starts Tomorrow Between Helix Ramp Bottom And 40 River Road - Z Brick Pavers Replaced With Asphalt Surface

Image of Main Street Road At Helix Looking North Tow Manhattan Park

According to the Roosevelt Island Operating Corp (RIOC):
Please be advised on Wednesday, September 12, 2012 Main Street roadway reconstruction will commence from the area below the Helix ramp to 40 River Road. The scope of project will involve removal of the existing Z-Brick Pavers and installation of an asphalt surface. The project will be performed in 3 Phases. During construction, the roadway will be condensed and will continue to provide two-way traffic at all times. Bus stops in the area of construction will be temporary relocated to ensure that passengers can board safely which may result in residual delays in service. The work is estimated to be completed by March 2013.

Sincerely,

Roosevelt Island Operating Corp Advisories Group
Image Of Motorgate Helix Ramp Bottom

UPDATE 7:30 PM - More from RIOC:
Due to the Main Street Reconstruction project that will commence tomorrow morning, there will be no parking between the bottom of the Helix to 40 River Road on both sides of the roadway. The current area designated for disabled parking will be relocated to a temporary parking area between 40 River Road (heading north) to the Octagon Soccer Field/Comfort Station.

The temporary no parking zone will be effect from Wednesday, September 12, 2012 until March 31, 2013.

Friday, November 25, 2011

Con Ed Conducting Emergency Road Work On Roosevelt Island From Southpoint Park To Front Of Goldwater Hospital - Q102 Bus Rerouted Untll Further Notice

Received the following advisory from the Roosevelt Island Operating Corp (RIOC) earlier today:

We have just been notified by Con Edison that they are conducting emergency road work from Southpoint Park (100 Main St) to the front of Goldwater Hospital (200 Main St). Therefore, the Q102 bus will be re-routed to pick up and drop off passengers in front of the Tram (300 Main St) until further notice.

Sincerely,

Roosevelt Island Operating Corp Advisories Group

Wednesday, December 22, 2010

Roosevelt Island Water Main For Blackwell House Leaking Into MTA Vent Shaft Reason For Road Work At Turnaround - Leak Now Fixed

Image of Blackwell Turnaround Road Work

Have you noticed the road work being done at the Blackwell Turnaround recently? Roosevelt Island Operating Corp (RIOC) Vice President Of Operations Fernando Martinez tells us why.
On December 8, 2010, NYC DEP gave us " Three - Day Notice to Cure". DEP discovered that the MTA vent shaft was being flooded by one of RIOC's water main lines. The water line feeding Blackwell House was leaking under the electrical wire bank. Water was getting into the wire bank and through the conduits to the vent shaft. We called a contractor to make the repairs. The water main for Blackwell House wasn't indicated on DEP or on our maps. In addition, the water main was difficult to trace because of an interference from other utilities under the pavement. The job was further complicated by the cold weather, heavy traffic, and a very thick layer of concrete. The contractor was also instructed to install shut off valves for the Blackwell House and sprinkle/fountain water lines. None existed previously. As of today, all of the piping is installed, which was inspected and approved by DEP. Today, the contractor will backfill the trench and cover it with the steel plates. The plates will be set even with the pavement. In the Spring, we will completely restore the road.
Image of Blackwell Turnaround Road Work