Tuesday, August 6, 2024

Roosevelt Landings Owner Renews Petition Seeking Approval From NY State Public Service Commission To Submeter Electricity In Buildings 1000 Rental Apartments - Residents Say Don't Submeter Until Landlord Fixes Broken Heating And Insulation System

In March 2024, the owners of Roosevelt Island's Roosevelt Landings complex

at 510-580 Main Street petitioned the NY State Public Service Commission to sub-meter electricity in the buildings approximately 1000 rental apartment units.

Previous Roosevelt Landings owners have sought approval of electricity sub-metering going back as far as 2008 and 2011, each time meeting strong opposition from building residents and local elected officials.

Several weeks ago, Roosevelt Landings managing agent C+C Management hosted an information session for building residents about their proposed renewed electricity sub-metering plan. I asked Roosevelt Landings Residents Association President Joyce Short and Vice President Romano Reid:

I'm preparing a story on the Roosevelt Landings sub-metering issue and recent meeting.

Do either of you wish to send a comment to be included in the article?

Ms Short and Mr Reid replied:

Our building has changed hands since 2014 when the Public Service Commission stayed our previous landlord's attempt to submeter. But little has changed to cure the critical issues raised by the stay. The new owners, L&M, and their Managing Agent C&C, seem to take our residents for fools. They held an "education" meeting in which they told residents they could change their light bulbs to LEDs and watch less TV, as if that would offset the absurd bills they'll receive to keep their families warm through the cold winter months. The landlord claims to have removed the burden of heat from our residents' shoulders, but residents know this claim is simply "lipstick on a pig."

Because our building is poorly insulated and has a porous skin that fails to retain heat, residents turn to plug-in space heaters that they will be charged for. In the summer, our building is equally poor at retaining air conditioning. Our a/c units are plug-ins and have to work overtime because of the insulation defects. Residents will be charged the entire expense for running their air conditioners.

Our residents have repeatedly experienced the dire consequences of their aging heaters that ignited fires in several homes. And because the last landlord failed to replace the summer/winter switches that enabled our air conditioners to run on a separate circuit, a/c fires have also become a common occurrence.

The landlord knows that the building's heating and insulation system is deficient. That's why they're investing millions of dollars into their current repair project. Their efforts are projected to take two years or more, but December of this year is their target date for submetering. Until they repair the building's problems, they'd like residents to bury their heads in the sand and pretend they're just trying to "green" our building. Our residents know that the only green in their submetering plan, however, is the financial, plug-in burden the landlord will dump on their shoulders.

Particularly for the building's subsidized, elderly, and disabled residents who will be charged for necessary medical devices, plug-ins as "added rent" could lead to their eviction. Protecting the homes of our vulnerable residents is a priority.

You can watch the insulation work taking place on the east promenade behind building 510. You can learn more about the building's submetering problems by linking to our webpage. And if you are a building resident, please sign the petition to stay submetering and write your comment to the PSC. You'll find the information you'll need on our webpage.

We're not saying don't submeter. We're saying don't submeter until you fix the problems with the building.

I spoke with Ms Short on August 4 in front of the exterior renovation work being done on the buildings.

I asked C+C Management about the sub-metering concerns raised by the Roosevelt Landings Residents Association:

A spokesperson for C+C Management replied:

“We have been communicating closely with residents about the plan to submeter non-heat electric usage at The Landings. This includes providing four educational sessions and residents have been notified that when submetering goes into effect, there will be a monthly rent reduction. We will continue to keep residents informed as this process moves forward and we are always available to answer any questions or concerns.”

C+C Management provided the following background on their submetering proposal.

  • The plan to submeter non-heat electric usage at The Landings was approved under previous ownership in 2014. On June 26, 2024, a letter was issued by the New York State Public Service Commission to begin the submetering process.
  • All residents will receive a monthly rent reduction when submetering goes into effect depending on the size of the apartment and calculated by the New York City Department of Housing Preservation & Development. A letter was distributed to residents on June 26, 2024 with this information.
  • Four educational sessions will be provided to residents prior to the start of submetering, with additional sessions available after submetering begins. The first educational session was held on July 8, 2024.
  • We have heard residents’ concerns about plug-in medical devices. The project team is working on developing a solution to address the matter.
  • Most New York City residents pay for their own electric usage through submetering. Submetering reduces pollution, combats climate change, and awareness of personal energy use can lead to energy conservation and utility savings.
  • The plan to submeter non-heat electric usage at The Landings was not contingent on the Exterior Insulation and Finish Systems (EIFS) work.
  • The EIFS work will go above and beyond in providing benefits to residents. The façade improvements will further reduce energy consumption and increase indoor comfort.
  • There were no heat violations in the 2023/2024 heating season at The Landings.
  • Residents should contact the management office at 212-838-4747 to report any maintenance issues.

Roosevelt Island's NY State Senator Liz Krueger's spokesperson adds:

Our office has been in contact with the Public Service Commission and we did receive this (hopeful) notification from PSC last week: 

 “We are discussing the sub-metering issue internally. My presumption is that the process will slow down and provide time for us to carefully check the compliance stuff....

Roosevelt Island's NY State Assembly Member Rebecca Seawright, Congressman Jerry Nadler, Ms Krueger and City Council Member Julie Menin sent this letter on behalf of Roosevelt Landings residents to building owner L&M Fund Management.

I also asked C+C Management:

According to the Carter Burden Senior Center, they have been told their outdoor patio garden will be closed very soon during renovations to the building's exterior wall and that the doors leading from the Senior Center to the outdoor patio will be sealed with no exit into the area possible. I'm told that the doors to the outdoor patio are "fire doors" which need to be accessible to the Senior Center in the event of an emergency. Is this true?
C+C Management replied:

The Senior Center patio doors are not fire doors and in the event of an emergency, there is an exit path on the DOB-approved Site Safety Plan. However, we understand residents’ concerns regarding access and will install a temporary bridge off the deck to Main Street. This temporary bridge will provide a path for residents to exit the patio.

Will update on the Roosevelt Landings electricity submetering issue when more info becomes available.

Thursday, July 19, 2018

Roosevelt Island Manhattan Park Low Income Residents Speak Up For Affordable Housing At Town Hall Meeting - "Who's Going To Help Us, Who's Going To Stand Up For Us" They Ask Local Elected Officials

2-4 River Road is the affordable housing component of the Roosevelt Island Manhattan Park buildings complex with many elderly and low income residents.


During the June 28 Roosevelt Island Town Hall meeting with elected officials (full video of Town Hall here), Manhattan Park 2-4 River Road residents expressed frustration at being ignored by the Manhattan Park building management and local politicians.

After a discussion about Westview building privatization and affordability plan, a 2-4 River Road Manhattan Park resident grabbed the attention of those attending the Town Hall by saying:
 ... we are affordable housing also and they haven't told us if they are going to renew the contract with HUD which will keep us affordable. Also they discriminate against us all the time. They have submetering, they are profiting off the submetering and it seems like no one will help us....

.... Our voices are not being heard, maybe because we are labeled as just low income tenants so they don't care about us. But we're working class people too that also live on Roosevelt Island for decades and it is not fair that we constantly get ignored on Roosevelt Island. We matter too. Our children matter too. Our families matter too.
About the Manhattan Park Management it was said:
 ... They do not recognize us as part of their complex....

... They don't even call us Manhattan Park. They won't let us form a tenants association.

Last week they had a tenants appreciation barbecue and they didn't even invite us. I put up a sign in the Hallway/lobby telling everyone to come and they ripped the signs down and finally decided to invite us to the Tenant Appreciation Barbecue the day before and that's only because I made the tenants of Northtown Phase 2 aware that there was a Tenants Appreciation Day..

Who's going to help us? Who's going to stand up for us?....


Following the Town Hall meeting, Roosevelt Island elected officials offered to provide assistance to the 2-4 River Road Manhattan Park residents.

Last week, I asked 2-4 River Road Tenant Leader Association Board Member Eneaqua Lewis:
Is there any update and did the elected officials get back to you on these issues? Kallos, Serrano, Seawright?
Ms Lewis replied:
The only elected official that contacted me was from Senator Serrano’s office. They have been very helpful. Also democratic leaders from the Four Freedoms Democratic club contacted me, Ben Wetzler and Lauren Trapanotto. Ben is helping me start a complaint against MP management.

MP tried to shut us down because they said they didn’t consider us a “Real TA”. We provided them with paperwork proving we were members of the National Association of HUD Tenants. They then permitted us to have the community room for July 17. MP hasn’t confirmed whether they will show up to answer our questions.

Several tenants on our board have been harassed by MP, including but not limited to having our renewal leases denied or put on hold. At the Town Hall meeting a tenant of MP told me that MP routinely tries to deny giving a lease to anyone who participated in TA’s. As far as I know MP doesn’t have a TA besides 2-4 TA.
According to 76 Assembly District Democratic Party District Leader Ben Wetzler:
This is an extremely frustrating instance of harassment. The management company is clearly in the wrong, and by targeting a new tenants' association they are trying to strip residents of their right to address safety and affordability questions in the future. But the worst part is the tenants at 2 and 4 River Road are having to deal with all the stress of this at home while trying to navigate the bureaucracy without much help. I've been trying to put them in touch with an attorney in case they need to go to court over any of the lease issues and I understand Senator Serrano's office got involved as soon as he heard about what was happening, but there really needs to be a more straightforward way to handle these and a place they can go for support.
In response to my inquiry a Manhattan Park Spokesperson said:
Submetering Update: “As we’ve stated in the past, Manhattan Park purchases electricity from Con Edison at a bulk reduced rate that we pass through to the residents of 2-4 River Road, without any additional charges. Electricity prices are set by the utility provider and rates fluctuate, but the fact is that we are in complete compliance with all Public Service Commission regulations. Furthermore, residents in the affordable units receive a flat monthly utility allowance set annually by HUD based on consumption of the prior year, which often exceeds their energy consumption.”

Tenant Association Concerns: “Manhattan Park management has recognized a tenant association for 2-4 River Road and has provided the opportunity for a public meeting to take place in common space on the property.”

Tenant Appreciation Day: “All Manhattan Park residents, including those at 2-4 River Road, were invited to the Tenant Appreciation Day and in fact many residents from the property in question attended the event. Notices were posted in every building throughout the complex with significant notice.”
Will update when more info available.

Monday, April 6, 2015

Decade Long Efforts For Affordable Privatization Plan At Former Roosevelt Island Mitchell Lama Island House Building Nearly Done Say Tenants Association - Residents Can Purchase, Remain Protected Renters Or Receive Buyout From Sponsor


As reported January 23, 2015:
Roosevelt Island's Island House rental building exited the Mitchell Lama program in September 2012.  As reported October 20, 2012 by former Roosevelt Island Operating Corp (RIOC) Acting President and current General Counsel Don Lewis:

... We are very pleased to note that, as result of several years of negotiations, Island House, a 400-unit affordable housing development on Roosevelt Island, will continue to remain affordable to its residents for the next 30 years. The Island House deal is historic in nature and marks the first successful conversion of a State Mitchell-Lama rental to affordable home ownership as a solution to a market-rate exit from Mitchell-Lama. Without the State’s intervention in extending affordability, apartments within Island House, a development at the threshold of leaving the Mitchell-Lama program, would have been allowed to be rented at market rates, severely affecting residents.

Under the Island House Affordability Plan, Island House, constructed in 1975 as one of the first four modern housing developments on Roosevelt Island, will exit the Mitchell-Lama program. The Affordability Plan, however, protects all current tenants by allowing them to remain in their apartments with future rent increases calculated in a manner similar to rent stabilized apartments. Rent protection will remain in effect for 30 years. The owner of Island House will apply to convert the building to Co-Op ownership. If the conversion is approved, current tenants will be offered the option to purchase their apartments at below market prices.

The Affordability Plan was initially drafted and agreed upon by the Island House owner and tenants. The Plan was later approved by a multi-agency working group that included: RIOC, which administers operations on Roosevelt Island; New York State Homes and Community Renewal (HCR), the State’s housing agency, which administers both the Mitchell-Lama program and the State’s rent laws; and Empire State Development (ESD), which in 1969, as the Urban Development Corporation, first leased the land under Island House from the City of New York. The Affordability Plan was the result of several years of negotiations among the agencies, the Island House Tenants Association, and owners’ representatives....
Island House is currently in the process of converting to a Condop (Co-op for residential units and condo for commercial units) under a non-eviction Affordability Plan.
Today, Island House Tenants Association Chair Graham Cannon reports:
It has been a long journey, at least a decade, but the Island House tenants are transitioning into the Affordability Plan that was envisioned long ago: some tenants will continue to be renters with strong rent protections for the next 30 years, some tenants will purchase their apartments at affordable rates. The Sponsor's offering plan was recently amended to offer a buy-out option and extend the exclusive period 20 days (April 20) so that tenants could review the options (rent, buy-out, purchase). The Attorney General will review and declare the conversion plan Effective. At that point, tenants will finalize mortgages, with closings expected to begin in the summer, and the co-op board will be elected. As of today, over 50% tenants have indicated that they will purchase their apartments, so the co-op board will be tenant-controlled with the sponsor holding under 50% of the board seats.

Fortunately for Island House tenants, we have had productive working relationship over many years that has included some tough negotiation with our Sponsor/Owner, represented by David Hirschhorn and moving forward we anticipate collaboration to maintain and expand the quality of life for all Island House residents. Our attorney Stuart Saft, who has literally Written The Book on coop conversion law, has helped guide use through the process with extensive knowledge, skill and effective negotiation. Our government entities, RIOC, ESDC, and DHCR (Rich McCurnin) have collaborated on this Affordability Plan and have created a template that can be used to preserve affordable housing in other Mitchell-Lama building complexes throughout the City and the State.

Concurrently, Island House will be engaged in window replacement and energy efficiency program. The windows will be energy efficient and similar to the present windows that slide, and the exterior will have modern treatments that update the faded yellow panels. Island House will also pursue submetering and rent reductions. Island House learned many things from the failed submetering attempts at Roosevelt Landings (Eastwood). Most importantly, Island House tenants already pay their full electric bills within their rents, so any sub metering plan is about apportioning costs that the tenants already pay (and coopters will pay), not adding new costs.

The submetering plan, in cooperation with the Sponsor/Owner, will NOT mark-up the low bulk electric rates, incorporate various energy efficiencies, (and we intend to pursue a range of additional conservation options after conversion) and the rent reduction strategy is intended to be revenue-neutral with a special focus by everybody involved in ensuring cost neutrality for those who remain as tenants.

We look forward to completing the transition to the Affordability Plan by late summer or fall this year."
More information available on the Island House privatization and affordability plan at this June 2012 post which includes video explaining the plan from May 27, 2012 Island House Tenants Association meeting.

Information on obtaining a mortgage for Island House residents is here.

Wednesday, March 13, 2013

RIRA Rep Seeks Answers To Manhattan Park Electricity Submetering - As A Result, Building Management Invites Rep To End Leasehold, They Don't Want Unhappy Tenants


Understanding Your Con Ed Electricity Bill from NY Times

Roosevelt Island Residents Association (RIRA) Manhattan Park Common Council Member Mark Lyon reports:
Manhattan Park and several other Roosevelt Island housing developments submeter electricity instead of allowing residents to purchase their electrical service directly from Con Edison.  While controversial, the NY Public Service Commission has strongly pushed submetering as an environmentally friendly measure that provides incentives for conservation and which also has the potential to offer electrical service at a lower rate than direct metering.

Unfortunately, efforts at submetering have neglected to consider a number of issues including the loss of incentives for landlords to provide energy efficient structures and appliances and the risk that some landlords may not be well suited to also performing the duties of a utility provider.  Coupled with the regrettable decisions of RIOC and its predecessor organizations in failing to require developers to make use of the existing island steam plant for effective, low-cost district heating, Roosevelt Islanders find themselves, in many cases, paying significant sums for electric heat to keep their apartments at a comfortable temperature during cold weather.

In December, the PSC adopted new rules for submetering. After reviewing these new rules, I thought it prudent, as a member of RIRA, to evaluate the impact of these changes on my electrical service and at similar submetered buildings on the Island. To legally submeter electrical service, individual PSC orders granting such authority to each development are required. As an initial step, I sought out the approved orders for all Roosevelt Island buildings.  I was able to easily locate the orders for The Octagon and Roosevelt Landings, but not for Manhattan Park.  When I submitted a records request, the PSC indicated that no such order could be found.

I reached out to the Manhattan Park management office, but received no response to my request for evidence of their approved submetering order.  As a result, I registered a complaint with the Secretary of the PSC, expressing my concern over the lack of an accessible copy of the order and also pointed out several issues with the way submetering is handled at the complex.  Many of the concerns I outlined have been shared with me by numerous other residents and affect everyone.  Fearing retaliation, however, few are willing to approach the management office with their concerns.

Manhattan Park responded by sending documents they claim indicate their approval to submeter and ignoring the other complaints.  In their response, they note that I am a “market rate tenant” with “market rate electrical consuming devices, the use of which [I] should pay for.” My complaints, however, are not about receiving free electricity. Instead, they are about ensuring management operates in accordance with the rules, laws and protections afforded to utility customers. Manhattan Park then invited me to end my tenancy (even though I have a year remaining in my lease) because they “prefer to have tenants who are not unhappy with their leasehold.”  I visited the management office and requested the attachments (which they intentionally omitted from my copy of the response), but the request was refused; I was instructed to contact the PSC for copies.

Finding this response more than a bit odd, I contacted the PSC to request copies of the attachments and to reiterate my concerns with the handling of submetering at Manhattan Park.  Those attachments have not yet been provided.  Even if the attachments to the letter demonstrated proper authority to provide submetering, there are still concerns to be addressed.  These include:

* Potentially charging more for electrical service than would otherwise be charged if tenants received directly metered service (violating the PSC's "rate cap" applied to most submetered service).

* Requiring a utility deposit before providing service (generally, utility deposits are allowed only in circumstances where a customer has a track record of missing payments).

* Failing to provide utility bills in a clear and understandable form.  Currently, the utility charges are added as a line item on our rent statements, showing a total kWh usage only.  PSC rules require additional information, including present and previous meter readings, on bills.

* Requiring excessive late fees.

* Delivering combined rent and utility bills on or after the due date.

* Failing to provide yearly Home Energy Fair Practices Act notices.

Two of the most critical issues with utility billing at Manhattan Park are the late distribution of bills and the lack of information about the service provided. Without access to the meters, historical readings or to the rates that will be charged, residents have no way to measure their electrical usage and anticipate the charges that might appear on their next bill.  Giving residents precious little time to pay before imposing late charges, while simultaneously providing almost no transparency creates a situation in which tenants can be easily abused.

The Public Service Commission is currently investigating these complaints.  Other complaints regarding overcharging, cross-wiring (where the power that you pay for is used for things outside your apartment like hallway lights or ventilation fans), billing practices (including threats of eviction or excessive late fees) or any other issues can be reported to the PSC online, by phone or by mail.  If others are experiencing issues with their submetered electrical service, I urge them to contact the PSC.
I asked Manhattan Park management if they wish to comment on the matter. They have not replied but will update if they do comment.

Thursday, September 22, 2011

NY State Public Service Commission Conditionally Approves Urban American's Electricity Submetering Plan For Roosevelt Island's Roosevelt Landings/Eastwood Buildings - What Does That Mean For Residents?

Roosevelt Island's Assembly Member Micah Kellner provides this update on plan by Roosevelt Landings/Eastwood Landlord Urban American to install electricity submetering in Roosevelt Landings apartments.

 Image of Mr. Kellner Speaking at 2009 Eastwood/Roosevelt Landings Submetering Forum

According to Mr. Kellner: 
The Fight Against Submetering Continues

I have long questioned the appropriateness of submetering in affordable housing, particularly in a building like Roosevelt Landings. The building's poor insulation and clunky electric heat will result in enormous electric bills for tenants who are just trying to keep warm in the winter.

In 2008, Urban American, the owner of Roosevelt Landings, applied to the Public Service Commission (PSC) for permission to submeter tenants. The PSC initially approved the application because they were not aware of the negative impacts submetering would have on tenants living in affordable housing. I immediately led a coalition of local elected officials and tenant leaders to request a stay preventing submetering from moving forward. The PSC granted the stay requiring Urban American to complete several different tenant protection and energy efficiency measures before they could unilaterally submeter tenants.

After a year of refusing to negotiate with elected officials and tenant leaders, Urban American filed a new submetering plan that claimed to meet the PSC's requirements. I submitted hundreds of pages of documents to the PSC outlining how this plan continued to fall short of the Commission's order. At the recent September 15th hearing, the PSC gave Urban American's plan conditional approval with the stipulation that they return to the commission with evidence that they have met the following requirements:
  • Install a thermostat in each apartment
  • Install EnergyStar refrigerators
  • Complete comprehensive energy efficiency improvements in the building through NYSERDA's Multi-Family Performance Program
  • Fully inform tenants of things they can do to save electricity
To date, Urban American has not made any effort to fulfill these measures. The landlord has been given three years and they have still not even installed a single thermostat. At present, I have no reason to believe that Urban American has, or will, comply with the PSC's order.

Throughout this process, I have fought to ensure robust protections for tenants. I helped Homes and Community Renewal (HCR) apply for and receive a voucher from the U.S. Department of Housing and Urban Development (HUD) to allow them to set utility allowances that reflect actual utility usage in the building. A utility allowance is a type of rent roll-back awarded to tenants who are now bearing the costs of utilities that were previously part of their rent. As opposed to the previous plan, which determined rates on a community wide basis, these new utility allowances will be based on electricity usage for similarly sized apartments in Roosevelt Landings and will include additional allowances for seniors and people with disabilities.

Submetering at Roosevelt Landings is not moving forward until Urban American satisfies the PSC's requirements. It is unconscionable that landlords are trying to dump their energy costs on tenants who are barely getting by, especially in these economically challenging times. I will continue to fight against submetering in affordable housing and for the protections that all tenants deserve.
I asked Mr. Kellner if the electricity charges would be included as additional rent for purposes of any potential eviction proceedings brought against a tenant. Mr. Kellner replied:
HCR will not allow Urban American to treat electric charges as added rent.
HCR is the NY State Homes and Community Renewal Agency which oversees the subsidized apartments at Roosevelt Landings.

I followed up by asking Mr. Kellner:
What about the market rate tenants and LAP tenants at Roosevelt Landings. Will their electricity charges be considered additional rent for purposes of possible eviction proceedings?
Mr. Kellner replied:
That is unclear, but we are working to insure it isn't considered rent. 
I asked Roosevelt Landings Residents Association President Joyce Mincheff to comment. Ms. Mincheff replied:
Our Assemblyman, Micah Kellner, has ducked the slings and arrows of Urban American to champion our cause once again! The tenants of Roosevelt Landings owe him a tremendous debt of gratitude!

No one from the Public Service Commission stepped foot in our building. If they had, they would know what a Professional Engineer and Certified Energy Manager knows about submetering our building: the building is so poorly constructed that even if thermostats were installed, the room temperature would rarely rise to the temperature they were set at in order to turn off the heaters.

1. The construction of the building, while architecturally unique, requires elevated levels of insulation, not the insulation level required by state code, the weakest level possible in the state of NY. Without appropriate insulation, rooms will simply not get warm.

2. Repeated jut-outs throughout the facade, varying roof heights, multiple exposures, concrete floors that conduct the cold, leaky window lintels, cheap windows, an overabundance of unrepaired expansion joints, antiquated heaters and an antiquated heating system all contribute to the barbaricness of the Public Service Commission's decision.

3. Common usage bundled into apartment wiring, regardless of the sworn self-serving affidavit the landlord submits, is evident to anyone who knows 1970s construction. The assumption that by some miracle, the 4 sets of buildings covered by Urban American's sub-metering application, even though they were built with the vission that the landlord would cover all electric costs regardless of where such wiring existed, is beyond absurd.

4. Education..... please! Our tenants don't need to be educated to know to put on a sweater to cut their energy costs.....They already wear them because their apartments are just plain cold. How cold? if you go to the laundry rooms in the winter, you'll see them wearing their gloves and jackets to wash their clothes. Heat simply is not retained inside our walls. Our elderly wear sweaters to bed at night. The insult of being educated to reduce your TV use by $3 per month while the landlord rips hundreds of dollars from your pocket by its failure to repair the insulation in your walls is outrageous. Shame on this landlord, and shame on the Public Service Commission!

The fact that the Public Service Commission reversed itself on the issue of not allowing the landlord to evict tenants when they can't pay their outrageous electric bills is downright Barbaric. It shows just how low the institutions of government, that one would think of as protective, will sink for a price. The old-boy network still reigns supreme and, for the affluent who can put big bucks in the right pockets, even Barbaric decisions can be bought.

While DHCR and HPD may have a solution to the eviction problem for subsidized tenants, and we will all pray that's the case, it may not solve the issue of eviction for non-payment of unfair and outrageous electric bills among LAP and Fair Market tenants.

The Roosevelt Landings Tenant Association has joined with all the former Putnam Portfolio buildings to oppose the landlord's farce masquereding as "greening" the building. Rather than reducing the carbon footprint by earnest conservation methods, the Public Service Commission has given permission to Urban American to lock in outrageous, wasteful energy practices and shown us all how blind they are to the needs of the public they are sworn to serve. We are not throwing in the towel. It is only a battle, not the war.

Joyce Mincheff
President
Roosevelt Landings Residents Association
I asked Urban American's representative at Roosevelt Landings Doryne Isely to comment. Ms. Isely replied:
Thank you for the opportunity to respond.
We’re pleased with the Public Service Commission’s decision and believe it reflects the work we did with residents, community leaders and elected officials to improve the plan. We’re committed to making Roosevelt Landings as environmentally sound a building as practically possible and look forward to working with the residents to achieve that goal.

Wednesday, August 24, 2011

Latest on Electricity Submetering at Roosevelt Island's Roosevelt Landings/Eastwood Buildings - Public Service Commission Recent Decision Requires Landlord Urban American To Demonstrate Thermostat Installation, Energy Efficiency Measures, No Tenant Evictions For Non Payment Of Electric Charges & More Before Subemetering Can Begin Says Assembly Member Kellner

The headline in this article from yesterday's Crains New York Business claimed:

Big landlord wins 1st round of submetering fight

Urban American wins state approval of its plan to install meters and have tenants at 1,800 apartments in Harlem pay for their own electricity, arguing it would save money and power; fate of 1,100 Roosevelt Island units uncertain....
According to the Crains article the NY State Public Service Commission:
... approved the company's plan for 1,800 apartments in three Harlem buildings. Based on unofficial meter readings from individual apartments, Urban American claimed that 70% of tenants would save money under submetering, rather than paying a fixed amount to cover energy. The state agreed....
The Roosevelt Island residents directly impacted by the submetering attempt by Urban American are tenants at Roosevelt Landings, formerly known as Eastwood which was privatized and taken out of the Mitchell Lama program several years ago.

Why do Roosevelt Landings/Eastwood tenants object to electricity submetering for their apartments? Roosevelt Island Assembly Member Micah Kellner answered that question in a June 2010 post.
... The submetering plan at Eastwood presented a host of problems for tenants. The building’s poor insulation and clunky electric heat would have meant that under submetering, tenants would be paying enormous electric bills just to keep warm in the winter. And the electric charges would be deemed as rent in tenants’ leases–meaning that tenants could be taken to housing court and potentially evicted for nonpayment of their electric bills. Tenants faced the prospect of having to choose between paying the rent and heating their homes...
After reading yesterday's Crains article, I asked Assembly Member Kellner for a comment.

 Image of Mr. Kellner Speaking at 2009 Eastwood/Roosevelt Landings Submetering Forum

Mr. Kellner replied:
The Crains’ article was factually inaccurate— All that the PSC has done with their most recent decision is reaffirm what they previously stated. Specifically, in order to submeter, the Landlord must:
  • Submit plans to the PSC demonstrating that tenants as a group are not disadvantaged financially as a result of submetering;
  • Conduct a consultative process in which all interested parties are involved. 
  • Submit documentation showing that individual thermostats have been installed in all apartments with certification from engineer;
  • Provide tenants with information concerning ways to reduce electricity usage;
  • Submit documentation that the buildings in question are participating in the NYSERDA Multifamily Performance Program (MPP) and all energy efficiency measures have been fully implemented;
  • Submit documentation of the installation of Energy Star refrigerators.
  • Clarify that no tenant can be evicted for non-payment of electric charges
We are still a long ways away from submetering in Urban America’s Harlem buildings and even further away in Roosevelt Landing. For all of buildings, the Landlord must return to the PSC to prove these conditions have been met. Until the day comes when thermostats are being installed in individual apartments, we will not know if they are truly serious about energy efficiency.
The Public Service Commission decision is not yet publicly available. Will post it when it is. The bottom line according to Mr. Kellner is that nothing has changed in regard to Urban American's attempt to submeter electricity usage at Roosevelt Landings/Eastwood due to this recent Public Service Commission decision.

Wednesday, May 4, 2011

Roosevelt Island Residents Association (RIRA) Meeting Tonight - RIRA Committee Reports on Red Bus Schedule/Stops/Strollers, Housing, Proposed Science Center and More

Image of April 2011 Roosevelt Island Residents Association Meeting

The Roosevelt Island Residents Association (RIRA) will be meeting 8 PM tonight, May 4,  at the Good Shepherd Community Center (543 Main Street). The Agenda for the meeting is below. As always, prior to the start of each meeting there is a public session in which any resident can come and address the Common Council Delegates on any issue of concern.

Also, remember that Roosevelt Island's NY State Senator Jose Serrano has Roosevelt Island constituent office hours just prior to the RIRA monthly meeting and on the first Wednesday of every month from 4 - 7 PM at RIOC Headquarters 591 Main Street.

If you have any questions to ask Senator Serrano's staff or are in need of any assistance that may require the help of your elected representative stop on by RIOC HQ. Also, bring photocopies of any paperwork related to your situation so that the Serrano staff can effectively and efficiently address the issue.

Below is the Agenda for the May RIRA Common Council:
May 4, RIRA Agenda

and RIRA Committee Reports.
RIRA – ISLAND SERVICES COMMITTEE (ISC) REPORT TO THE COMMON COUNCIL MEETING, 5/5/11

Updates on the key issues ISC is working on:

Red Bus –Schedule, Stops, Strollers – RIRA (President, Planning & Island Services Committees)met with RIOC (Martinez & Cy Opperman)| on 4/25/11 to review Red Bus. We agreed on the following: Schedule – The buses are now operating close to schedule. The main problem causing delays is double parked vehicles on Main St. in Northtown. RIRA suggested that RIC might want to prohibit parking on Main St. at selected locations from 7 am to 9 am on weekday mornings. The key to maintaining a schedule is proper headway between buses. Opperman or another RIOC person will meet or dispatch buses at the Octagon and/or the subway/Tram stops during rush hours.

Stops- The East Tram bus stop will be the principal place to discharge passengers and load passengers. Buses will also dwell here as necessary. The West Tram bus stop, at the kiosk, will probably be retained as a service for Goldwater employees and other passengers from Sportspark and the tennis facility.

Strollers – RIOC agreed to studying and changing the policy of not letting strollers on during rush hours. We expect that the no-strollers policy will be eliminated or substantially modified in the next few months. If the policy is changed, RIO\C will need help from RIRA in explaining to parents and other residents proper protocol for using the buses during rush hours.

Pedestrian Safety Barrier on RI Bridge – We have not received an official response From the NYC DOT to our letter outlining a safety problem at the RI Bridge. However, our “informers” at DOT say that the issue is circulating around the organization.

Public Library – Senator Serranoʼs office informed us that the grant for the Public Library is expected to be $300K.

Aaron Hamburger, Chair - ISC

February 2011: RIRA Housing Committee Minutes
By Russell Fields

The Committee met on  2/27/11 and the attendees included Lorraine Williams, Romano Reid , Russell Fields, Ellen Polivy, and Committee Chairwoman Helen Chirivas.

Our Committee met to consider the following:
1.    HEAP – Home Energy Assistance Program‐ for low income utility expense assistance. Ellen and Steve Heller are planning a meeting with a lawyer from the Urban Justice center to assist eligible residents of all buildings with filing problems.

2.    Discussion of Jose Serrano’s submetering legislation securing that all housing allowances will be fair to all affected tenants in NYS; currently in State Senate Committee.

3.    Formation of a Housing Subcommittee called, HOUSING CONCERNS AND CHALLENGES to deal with the following issues (see attached resolution) a) Adequate disclosure of utility status for each building when referring to the building in common usage,    b) Accepting housing related complaints at the RIRA mail box and by email for referral to building committees, state agencies, and designated parties and follow‐up thereon. c) Conducting electronic surveys on housing issues and satisfaction ratings for all buildings and publishing the results.

4.    In addition concerns over the ongoing affordability were discussed including possible solutions.

5.    There is considered to be inadequate disclosure in clear language as to the how the buildings are heated and if their utility bills are submetered. We are concerned that non disclosure might cause a surprise burden to potential tenants. We believe that for a potential tenant to make an informed decision, this information must be available at the time of decision making. Russell is researching which buildings already disclose this information on their websites or in their marketing literature and what they say.

Southern Development Review – a sub-committee of the RIRA Planning Committee April 28, 2011

Last Thursday, we had the first in-person meeting of the SD (Science Center) Sub- committee of the RIRA Planning and Resident's council. We agreed that there are the following broad categories of discussion.
•    Transportation - during construction and once the new facility opens.
•    Integration - this includes ideas about the RFP-winner being able to leverage existing facilities either currently on the island or planned for it, ingress/egress for the new physical plant (i.e. a strong preference not to have a gated community inaccessible to residents) and other items of discussion.
•    Facilities - this dovetails with the above.
•    Logistics - among other things this includes thinking through waste removal via the "avac" system, construction loads over the helix roadway from Queens and the issues around the possibility of simultaneous construction projects if Southtown's planned additional residences are being built at the same time.
•    Youth - how could the science center be of value to our youth? What might be a reasonable partnership with bid winner in terms of local schools and programs?
•    Idealized conceptions - while there are many, one of the most interesting is the suggestion of a bio-medical engineering program to be developed to work in conjunction with Coler hospital at the North end.

Our next steps are to further refine each line item under the above and work with RIOC to arrange a discussion with NYEDC regarding our ideas and suggestions. We will be meeting again within the next few weeks. If any island resident would like to join the committee now is the time. Given the announced schedule, we need to work quickly to assist in optimizing the outcome for Roosevelt Island and the eventual designee."

Denise Shull Chair - SD sub-committee May 1, 2011
If you are interested in learning more about what is happening on Roosevelt Island, come on down to tonight's RIRA meeting. Sometimes, it can get quite exciting, in a Roosevelt Island sort of way.

I am unable to attend tonight's meeting so if anyone wishes to report on what happened please let me know.

Thursday, February 5, 2009

Eastwood/Roosevelt Landings Residents Seek RIRA Support In Action Against Outrageous Submetered Electricity Charge Increases By Urban America

Image of 2/4 Standing Room only RIRA Meeting

I was shocked when I walked into the Good Shepherd Community Center lower level room last night for the monthly Roosevelt Island Residents Association (RIRA) Common Council meeting to discover it was packed with people, standing room only.

I soon learned the reason for the large attendance was that many residents of Eastwood (renamed Roosevelt Landings by it's new owners Urban America) were there seeking support from RIRA to protest the incredibly huge sample electricity bills they just received under the new submetering plan for the building. According to some of the Eastwood residents, monthly electricity bills are as high as $1, 000 (that is not a typo) for a 3 bedroom apartment and $500-600 for a two bedroom apartment.

Eastwood/Roosevelt Landings residents were urged to attend this meeting.

EMERGENCY MEETING!

ROOSEVELT LANDINGS RESIDENTS ASSOCIATION

General Membership

Good Shepherd Church

Saturday, 2/7/09 at 2 PM

Please bring the following:

A copy of your sample electric bill. Please write on it

  • the number of bedrooms in your apartment
  • whether you face North, South, etc,
  • whether you are located Mid Hallway, Elevator Vestibule or Far End of Hallway
A note to RLRA concerning any complaints you have about your heaters. Identify the dates of your complaints to management and 311
A donation so that RLRA can shoulder the costs to fight this fight!

A representative of Assembly Member Kellner's office was in attendance and urged all residents to stick together, collect information about their electricity bills and make sure that Mr. Kellner receives the collected information.

Following the meeting a reader and Eastwood/Roosevelt Landings resident forwarded the following letter sent to building management:
I am deeply disturbed by the sample utility bill that I received recently for the month of December 2008 in the amount of $476. The amount in particular has shocked me, and I feel that I have to address certain concerns I have with my apartment.

My concerns are so numerous I have numbered them for you. They are as follows:

  1. My first concern is the efficiency of the insulation of the new windows installed last fall.
  2. Although I submitted the form for winterization, as requested, the maintenance staff never performed that task.
  3. The baseboard electric heaters, installed some thirty years ago, are not energy-efficient and need to be replaced.
  4. In addition, the heaters do not have any sensors, are running all day, and overheat.
  5. My refrigerator, which has been in place for at least the ten years of my tenancy, is not energy-efficient and likewise needs to be replaced. The milk freezes and the ice cream melts.
  6. While I am writing this letter, let me also mention my concerns with the continuously dripping bathtub, which Maintenance has yet to repair.
  7. Grout is heavily missing in the shower, something Maintenance has yet to repair.
  8. Newly installed kitchen cabinets have gaps at the floor, leading to unsanitary condition, an issue maintenance has yet to address.
  9. In addition, one of the kitchen cabinets cannot open due to wrong measurement.
  10. Furthermore, I wish to bring to your attention the cockroach situation in the bathroom, which Maintenance has yet to address.
  11. There continues to be a pigeon infestation in the air conditioning unit. This has been going on for two years now, and although Maintenance has addressed this, the pigeons are still there.
  12. The electrical outlets in two bedrooms are loose and serious safety hazards
  13. The doorbell is not working.
  14. Finally, I wish to complain that when I tipped the maintenance staff to carefully remove a heavy file cabinet so as to not scratch the floor, they simply dragged it while I was gone, thus scratching my floor.


I would like to know what Housing Management can do to resolve these issues.

Sincerely,

An Eastwood Resident

Monday, December 1, 2008

Kellner, Serrano, Maloney & Lappin Support Eastwood Tenants Objections to Urban America's Plan For Electricity Submetering

Image of Eastwood (Roosevelt Landings) from Bridge and Tunnel Club

Assembly Member Kellner, State Senator Serrano, Congresswoman Maloney and Council Member Lappin sent the following letter dated November 25, 2008 to Urban America's CEO Phillip Eisenberg expressing concern regarding the electrical submetering at Eastwood (Roosevelt Landings).
As elected officials representing Roosevelt Island, we write to express our strong concern with the plan set forth by Urban American to begin submetering of the electricity at the Eastwood housing complex. While we understand that submetering can promote more efficient use of energy in residential buildings, we believe that given the particular circumstances at Eastwood, going forward with submetering at this time would expose tenants there to an unacceptable degree of risk.

There is currently not sufficient evidence to demonstrate that adequate tenant protections will be in place prior to Urban American’s January 2009 target date for the beginning of individual billing. We are particularly concerned because the building is old, poorly insulated, and its heating system is electric. Many of its residents are seniors and people with disabilities, on fixed incomes, who often spend a great deal of time at home in their apartments. The transition to submetering raises the prospect that these tenants will be unable to afford to heat their own apartments.

Section 8 tenants are entitled to a utility allowance, to be administered by the New York State Division of Housing and Community Renewal (DHCR), according to which tenants’ rent will be lowered by an amount meant to be sufficient to offset the cost of a reasonable amount of energy usage. Urban American has pledged to match this allowance for tenants on the Landlord Assistance Program (LAP) and market rate tenants. However, we do not yet know what the allowance will be. At a community forum on October 16, DHCR representatives were unable to suggest what it might be. The allowance is based upon a formula set by the United States Department of Housing and Urban Development, for the entire portfolio of New York City buildings administered by DHCR. However, Eastwood is the only one of these buildings to be electrically heated. We note that while the building was in Mitchell-Lama program, management repeatedly testified to DHCR during the Budget/Rent Determination process that electricity constituted a particularly significant expense at Eastwood, primarily because of the cost of electric heat.

Not only do we have no estimate of the allowance, we have not seen sample billing or any analysis to permit a reasonable estimate as to what amount would be adequate given Eastwood’s unique circumstances. Additionally, we do not know what price tenants will be paying per kilowatt hour, given that Urban American has shut tenants out of the process of negotiating the bulk electricity rate. Further, Urban American must be specific as to how tenants are to be billed. It is important that submetered electricity not be billed as rent or “additional rent” if doing so would expose tenants to eviction proceedings in the event of unpaid utility costs.

Additionally, at the October forum and in individual comments to our offices, tenants have complained about faulty heaters, a lack of thermostats to properly control the heating level, energy-inefficient appliances, and poor insulation in apartments, including around air conditioner sleeves. Urban American has committed to repairing all of these defects for tenants who ask them to do so. However, until there is convincing evidence that these problems have been fully addressed, it would be inappropriate to go forward with submetering.

For these reasons, it is our position that Urban American must not begin individual billing for tenants’ electricity usage until the following has taken place:

• The New York State Energy Research and Development Authority has undertaken a comprehensive analysis of energy usage and efficiency in the Eastwood complex, so that we can determine the major sources of energy usage in the building and how much of it is accounted for by heating;

• The proposed utility allowance can be judged against the bulk electricity rate;

• At least two winter months of sample billing have been conducted, so that it is clear that the utility allowance is sufficient to offset residents’ actual electricity costs, including the cost of heating; and

• Urban American has completed all the efficiency upgrades and apartment repairs
requested by tenants as per its public commitment.

If it is determined that the utility allowance is sufficient to fully offset the cost to residents of heating and other reasonable electricity usage, we will not object to Urban American’s plan to proceed with submetering at Eastwood. However, if it is projected that costs to tenants will significantly exceed the amount of the utility allowance, the submetering plan would amount to a de-facto rent increase. In that case, Urban American would need to fundamentally re-consider its plan.

As of the date of this letter, it is our understanding from the New York State Public
Service Commission that Urban American has not yet submitted its petition for approval of submetering at Eastwood. For the protection of the building’s tenants, we ask Urban American not to submit the petition until the above steps have been taken. While improving energy efficiency is a laudable goal, no one should be forced to freeze in the winter in order to afford their rent.

Thank you for your attention to this matter. You may direct your response to the Office of Assembly Member Kellner, at 315 East 65th Street, New York, NY, 10065.
Here is link to Roosevelt Landings (formerly Eastwood) web site and apartment listings though it has not been updated since May 19, 2008.

Monday, November 24, 2008

Roosevelt Island Electricity Bills - Submetering at Eastwood Fears and Manhattan Park Complaints

Understanding Your Con Ed Electricity Bill Image From NY Times

With winter coming, keeping warm means increased energy usage together with higher Con Ed electricity charges. Assembly Member Micah Kellner reports in his newsletter on the situation confronting residents of Eastwood, now known as Roosevelt Landings:
Recently, residents of the Eastwood complex on Roosevelt Island were informed by their management company, Urban American, that the building would be converting to sub-metered electricity. This means that tenants would be billed individually for their household’s electricity usage. Urban American intends for this transition to take place early next year.

I have serious concerns about this process, and how it will affect tenants.
On October 16th, I participated in a town hall meeting, along with Eastwood tenants, at the Good Shepherd Community Center. The meeting was an opportunity to ask building management questions about the sub-metering proposal, as well as to hear from the state agencies involved. As a result of this meeting, and the numerous comments I have heard from residents there, I do not believe that the building is ready to go forward with sub-metering.

Too many tenants still have energy-inefficient appliances and faulty electric heaters, these are not personal items, rather these are items that come with the apartment and the management company is responsible for them. Urban American has promised to replace inefficient appliances and to fix heaters and thermostats for any residents who make a request to them. If you are an Eastwood tenant and you have made a request like this to management but they have not responded, please call me.

It is imperative that we have a clear picture of overall energy use in the building. The building’s heat is electric, so it is essential to ensure that tenants do not face unreasonably high utility bills just to stay warm in the winter. It concerns me that so many apartments are poorly insulated and Urban American needs to address this. I have asked the New York State Energy Research and Development Authority to conduct a full survey of energy use and efficiency in Eastwood, so that residents are not penalized by faulty design or maintenance.

I am also concerned that we do not have a real sense about how billing will work under this new system, given the complicated system of affordable housing programs that are integrated into the Mitchell-Lama’s accounting already. Will the utility allowance calculated by state and federal agencies be enough to compensate tenants for a reasonable amount of electricity usage? I have asked New York City Comptroller Bill Thompson as well as the New York State Division of Housing and Community Renewal to work with Urban American to ensure that residents are protected.
Saving Mitchell-Lama explains how submetering impacts residents in Mitchell-Lama housing:
... Your rent is reduced by a fixed amount established by the State's Division of Housing and Community Renewal. (Click on the blue lettering to see DHCR's fact sheet and the exact rent reduction numbers.)

The landlord buys electricity at the bulk (cheaper) rate from the provider (like Con Ed or some other Energy Service Company provider - or "ESCO"), and then is supposed to charge the tenants the same rate plus a $4 administrative fee -- but there is currently no way to check how much the landlord actually paid. The landlord is allowed to charge up to the amount you could be charged if you were billed directly by Con Edison at the full residential rate. (If the landlord buys electricity from two or more providers, there may be two or more bills for him to pass along to you.)

The amount you spend each month on electricity is listed as a separate part of your rent bill, and you pay it with your rent. In some cases, you get a bill directly from the company administering the submetering bill, and you would pay that company directly....
Residents of Manhattan Park have some complaints about their electric bills too and The NY Times explains how to read your Con Ed electricity bill

UPDATE:12/1 - Assembly Member Kellner, State Senator Serrano, Congresswoman Maloney and Council Member Lappin sent this letter to Urban America's CEO Phillip Eisenberg expressing concern regarding the electrical submetering at Eastwook (Roosevelt Landings).