Tuesday, November 1, 2016

Residents Spot Large Barge And Crane In East River Next To Roosevelt Island Southtown Riverwalk Buildings - Ask What Is Going On?

Residents spotted a huge crane mounted on a barge in the East River (Queens side) adjacent to Roosevelt Island's Souththown Riverwalk buildings


today with plenty of workers in construction hard hats and yellow vests


nearby.


What was going on? Some thought it might be fixing Hurricane Sandy damage,
the beginning of work on the Roosevelt Island East River Ferry Dock or start of construction on new Riverwalk building 8.

I asked Roosevelt Island Operating Corp (RIOC) President Susan Rosenthal what was going on. Ms Rosenthal provided the answer:
New York City Transit and its sub-contractor Simpson & Brown are replacing anodes on the East Side of Roosevelt Island bulkhead to protect the steel shell of the 63rd St tunnel.

They have a permit from RIOC.

Friday, June 13, 2014

Large Crane Transported By East River Barge For Construction Of Hudson Related Southtown 266 Unit Market Rate Rental Riverwalk Building 7 - Crane Too Heavy For Roosevelt Island Bridge Helix


A large barge pulled up aside Roosevelt Island's Southtown Riverwalk Buildiing 7 construction site this morning.

Image From RI On Crackberry

According to the Roosevelt Island Operating Corp (RIOC):
On Friday, June 13 from 7 AM until 12 PM, a large crane will be transported by barge to the Riverwalk Building 7 construction site. During this time, a section of the East Promenade to the west of the site will be closed to the public. Flag persons will be posted onsite to direct pedestrian traffic.
The crane


was lifted from the barge


and deposited inside the construction site.



As Hudson Related's Sara Willard explains:
The crane is for our superstructure/concrete contractors to complete the remaining floors at the building.  We are currently on floor 14.  We project to "top out" the floors in late July, by which the barge will be back to pick-up the crane.


After delivery of the crane, the barge headed back south on the East River passing underneath


the Queensboro Bridge.

The Crane was barged because it was too heavy to be transported over the Roosevelt Island Bridge.

On March 3, 2014 the Riverwalk Building 7 construction site was only a hole in the ground.

Image Of Roosevelt Island Riverwalk Building 7 Construction Site March 3

More on Roosevelt Island's Riverwalk 266 unit market rate rental Building 7 from previous post.

Friday, June 4, 2010

Roosevelt Island Traffic Advisory For Tram Area Caused By Mechanical Problems With Crane

Aerial View of Roosevelt Island Tram Crane

Received the following advisory from RIOC:
Due to mechanical difficulties with the crane at the Tram, the West Channel Drive from Sports Park to the Tram will remain closed until further notice. Public Safety Officers will be stationed at the site in order to direct traffic.

Sincerely,

Roosevelt Island Operating Corp Advisories Group
I asked RIOC VP Of Operations Fernando Martinez:
What are the mechanical difficulties with the Crane referenced in RIOC Advisory Below.

Any estimate as to how long the temporary traffic patterns will remain?
Mr. Martinez replied:
The computer on the crane did not allow the boom to completely retract to the folded position.

Thursday, June 3, 2010

RI Bridge Weight Restictions For Cranes Cited By POMA As Reason For One Month Delay In Roosevelt Island Tram's Return To Service


You Tube Video of Nighttime Tram Ride With Charlie Parker & Miles Davis

Roosevelt Island residents and everyone else wishing to ride the Roosevelt Island Tram, with or without Charlie Parker and Miles Davis, will have to wait longer than originally planned and promised for the Tram to return to service.

As reported in yesterday's post, the return of the Roosevelt Island Tram to service, originally scheduled for late August/early September, has been delayed to at least October 1. According to Roosevelt Island Operating Corp. President Steve Shane:
Tram: At this writing, fourteen weeks after shutdown, POMA advises that the schedule for reopening has fallen behind by about a month to October 1. The City’s stricter enforcement of weight restrictions on bridges as applied to crane mobilization is being blamed for the delay. The Contractor is working on alternatives. Station work proceeds apace at both ends. A crane is to be delivered by barge on June 2. Work will proceed to replace the top of the Island tower and then, presumably on to Manhattan. Preliminary architectural design for station improvements continues. There will be a community presentation for reaction, comment and decisions about trade-offs.
Crane Being Assembled Today

Yesterday, I asked Mr. Shane:
If there were problems securing a permit to carry the crane over bridge due to weight restrictions, why did POMA wait until today to bring it on RI by barge?
Mr. Shane replied:
I don't know, but availability of the barge and the crane were very big logistical problems. The problems with the bridges only became an issue within the last month. The barging option is very expensive. You should have been there to see it.
As recently as last May 21 I asked Mr. Shane if the Tram Modernization Project will be able to meet it's September 1 scheduled opening date. Mr. Shane replied:
POMA continues to state that the delay can be overcome. I grow increasingly skeptical. We push every day and are staying on top of the situation, but the work other than on the towers goes on. When it is on the critical path to ultimately delay delivery becomes a matter of judgment as to whether, when and where the effort and resources will be committed to make up the lost time.

POMA is contractually obligated to deliver the system and would be penalized with daily penalties as liquidated damages for late delivery in accordance with the terms of the contract. POMA would likely take a legal position to argue force majeure, but without an official embargo from the City, RIOC would obviously dispute their claim. So it goes in the construction business. We continue to push POMA and at the same time, try to assist with the City agencies having jurisdiction. Much bigger issue Citywide than RIOC"s & POMA's problem at both ends of the Tram. In everyone's best interest to get the project done as quickly as possible.
Last February 25 , Mr. Shane wrote in his RIOC column (Item 2) that all permits were secured before the Tram was taken out of service:
Tram:A. On schedule for shutdown after this Sunday on Monday morning, March 1 at 2 AM (3 Days!!!) and reopening by September 1, 2010. The plans for crane usage, street closings (including the upper ramp of the Queensboro Bridge), permitted times, traffic control and safety precautions, all as submitted to the Departments of Buildings and Traffic have been reviewed and permits were issued this week.
The fear of many Tram users was expressed in this Paul Sahner Tweet:
The Roosevelt Island Tram's estimated date of completion has been pushed back a month. Thus the slippery slope begins.
but no sympathy from Fake MTA's Tweet:
Can't you Roosevelt Island weirdos hang-glide or jet-pack over, or something? Get serious!
Apparently Fake MTA was not aware of RIOC's secret paragliding plan to temporarily replace the Tram.

Wednesday, June 2, 2010

Roosevelt Island Tram Resumption Of Service Pushed Back To At Least October 2010 - Crane Arriving Today, Main Street Traffic Advisory For A Week

Learned today that RIOC has been advised by POMA that work has fallen behind on the Roosevelt Island Tram Modernization Project. The scheduled resumption of service has been pushed back from late August/early September to October 1. Will have more on this later.

Meanwhile, received the following Advisories from RIOC regarding the Roosevelt Island Tram Modernization Program:

Please be advised today, Wednesday June 2, 2010, the crane for Tower 3 will be arriving today by barge between the hours of 1:30 p.m. and 5:00 p.m. Total delivery and assembly time for the crane will take between 4 to 6 hours.

There will be some delays with regard to the RIOC Red Bus and Q102 buses as well as traffic delays. Please allow for extra travel time.
and:
Please be advised effective 6:00 a.m. Thursday, June 3, 2010, West Drive Road will be closed for South Bound Traffic and vehicles will be re-routed to New Main Street. The loop will become one way for a period of at least one week. Tram Road will be closed from the Fountain turn around to West Drive due to the presence of a crane that will be working on the replacement of the top of the Tram tower. Traffic will be allowed to continue around Sports Park or Goldwater Hospital to West Drive.

A detailed map is attached for your convenience.

Friday, May 21, 2010

Lack Of NYC Construction Crane Permits Delay Roosevelt Island Tram Work - Increasing Skepticism Tram Will Resume Service By Scheduled September Date


You Tube Video of Time Lapse Crane On NY Pier

Uh Oh - is it time to start being concerned that the Roosevelt Island Tram may be out of service longer than scheduled and not be ready to resume daily Tram service operations over the East River as promised for late August/Early September?

It appears that the Tram Modernization Program contractor Poma, which has little or no experience on New York City projects but is relying on others to guide it through the inner workings of local construction logistics, is having dificulty securing the required crane mobilization permits in a timely manner.

Here's why Roosevelt Island residents may need to get worried that the Tram will not be ready as originally promised. Yesterday, in preparation for a post on this weekend's scheduled Queensboro Bridge and Second Avenue/surrounding streets lane closures due to work on the Tram, I asked RIOC President Steve Shane:
...wanted to check that the RIOC advisories regarding lane closures for Queensboro Bridge and surrounding streets scheduled to begin this weekend are going forward and not changed before I post them on blog.
Mr. Shane replied:
The advisory for lane closures is rescinded as the work on 60th street has been postponed due to the continuing difficulties of POMA (and others) in obtaining crane mobilization permits in Manhattan.
I followed up with:
As of now, do the problems obtaining crane permits delay the resumption of Tram service from the scheduled late August/Early September date?

If not, at what point will the failure to obtain crane permits result in pushing back the scheduled start of Tram service?

Also, is POMA contractually penalized if they fail to deliver Tram Service by the Early September date if that failure was caused by the non- timely issuance of crane permits by the City or other appropriate governmental bodies?
and Mr. Shane responded:
POMA continues to state that the delay can be overcome. I grow increasingly skeptical. We push every day and are staying on top of the situation, but the work other than on the towers goes on. When it is on the critical path to ultimately delay delivery becomes a matter of judgment as to whether, when and where the effort and resources will be committed to make up the lost time.

POMA is contractually obligated to deliver the system and would be penalized with daily penalties as liquidated damages for late delivery in accordance with the terms of the contract. POMA would likely take a legal position to argue force majeure, but without an official embargo from the City, RIOC would obviously dispute their claim. So it goes in the construction business. We continue to push POMA and at the same time, try to assist with the City agencies having jurisdiction. Much bigger issue Citywide than RIOC"s & POMA's problem at both ends of the Tram. In everyone's best interest to get the project done as quickly as possible.
If Mr. Shane is becoming "increasingly skeptical", I am deeply worried that Roosevelt Island residents may have to wait much longer than the planned 6 months for the Roosevelt Island Tram to return to service.

Mr. Shane also addressed the Tram issue as it relates to cranes and weight restrictions on the Roosevelt Island Bridge in his most recent RIOC President's Report: Tram (Item 2):
At this writing, twelve weeks after shutdown, POMA advises that construction is still on schedule for reopening by September 1, although the City’s stricter enforcement of weight restrictions on bridges as applied to crane mobilization has resulted in some delay. The Contractor is working on alternatives. Station work proceeds apace at both ends. RIOC has engaged BL Companies to do some preliminary architectural design for work on the two stations after the system is back in operation. There will be a community presentation for reaction and comment as we go forward.
Let's hope and do all we can that these invisible ghost spirit people are not the only Roosevelt Island residents using the Tram come this September.
Design Image of RI Tram Station From RIOC and BL Companies

More on Roosevelt Island Tram Modernization Program from RIOC.