Showing posts with label seawall. Show all posts
Showing posts with label seawall. Show all posts

Monday, April 22, 2024

Residents Ask Why Was Chain Link Fence Installed Blocking Access To Roosevelt Island East River Eleanor's Pier And Will Pier Tables And Chairs Return When It's Fixed?

Last Friday, Roosevelt Island residents noticed chain linked fencing being installed at Eleanor's Pier on the East River waterfront promenade

 
and asked:
  • Do you know what happened here? It’s fully fenced
  • What is this fencing???? So strange they would close the entire pier 😔 

Last month, a portion of the Eleanor's Pier seawall railing collapsed.

On April 1, Roosevelt Island Operating Corp (RIOC) Communications Director Bryant Daniels replied to my question asking what happened and reported:

On Saturday evening an individual was holding onto one of the railings on Eleanor’s Pier when it collapsed back onto the pier. Thankfully, that person was ok and did not require medical attention. No other individuals were involved in the incident, and nothing went into the water. 

RIOC has cordoned off the entire area for public safety purposes and begun investigating why the railing collapsed, and whether the rest of the railings will require any remediation work to ensure their structural integrity. We don’t yet have a timeline for the repair work but will be sure to keep the community up to date when we know more. In the meantime, for those visiting the pier, we are asking everyone to please adhere to our temporary boundary and not cross into the cordoned off area.

Subsequently, additional problems were discovered at the Pier which required it to be closed for safety precautions. 

Also, several residents have asked:

Do you know what happened to the chairs in Eleanor’s pier? They disappeared slowly and never came back.

Do not know yet RIOC's plan to fix and timetable to re-open the Pier or if the tables and chairs will return.

Will update when more info becomes available.

The same pier seawall railing area collapsed in February 2023

and the Roosevelt Island boat prow is still closed 

a year after the damage was discovered in April 2023.

Wednesday, July 22, 2020

RIOC Southpoint Park Shoreline Restoration Project Tour Answers Questions From Assembly Member Seawright, Borough President Brewer And Residents On Crumbling Seawall, Public Access To Waterfront, Removing Trees, Soil Contamination Cat Sanctuary & More - Watch Video Of The Tour To Find Out What's Going On


Last Saturday, July 17, NY State Assembly Member Rebecca Seawright, Manhattan Borough President Gale Brewer, Roosevelt Island Operating Corp (RIOC) Chief Financial Officer John O'Reilly together with RIOC staff joined with local residents on a tour of the Southpoint Park Restoration Project. According to Ms Seawright, the purpose of the tour was to:
... better understand and address the RI community concerns of the upcoming Southpoint Shoreline project...
As previously reported, some Roosevelt Island community members, led by the Wildlife Freedom Foundation (WFF) President Rossana Ceruzzi, vigorously oppose the Shoreline Restoration project to fix the crumbling seawall and provide greater waterfront access to the public because they claim the project will:
... destroy 325 Trees and decimate the wildlife living in the area....
RIOC answers that the Southpoint Park Shoreline Restoration Project:
... preserves the natural habitat and wildlife that currently exist, while also enhancing the surrounding greenspace paths. The required work involves the removal of toxic soil that has been inundated with overgrown landfills, choked with invasive vegetation, that must be removed before the seawall can be repaired. Roughly 99 small trees (ten inches in diameter) will be removed and replaced with 79 trees. The tree removal is necessary to access the area to be remediated. In addition, 870 shrubs, 645 other indigenous plantings, and approximately 14,500 sq. ft. of new grass that will encourage more wildlife to visit the shoreline. This project must be completed in order to prevent further deterioration of the seawall due to the ever-increasing impacts of climate change....

... Due to community concerns of the project’s potential effects on local flora and fauna, we are pushing the start date back. In the interim, RIOC will provide the community with regular updates on the project through meetings, press releases, its website and social media....
Here's portion of the Southpoint Park Shoreline Restoration Project tour.

Part 1 - Questions raised about need for cutting down trees, soil contamination and moving Cat Sanctuary to a new location.



Part 2 - RIOC shows off new Southpoint Park WFF Cat Sanctuary.

Tuesday, July 7, 2020

RIOC Announces Temporary Pause Of Roosevelt Island Southpoint Park Shoreline Restoration Project To Provide Community With More Info - Assembly Member Rebecca Seawright To Host July 14 Virtual Town Hall With Acting RIOC President For Community To Ask Questions On Project

A Roosevelt Island resident asked yesterday:

I'm trying to better understand the posters around talking about 320 trees being cut down in Southpoint Park to make way for more walking paths. There seems to be plenty paths down there already. Do you have more information on this plan?

Today, I asked Roosevelt Island Operating Corp (RIOC) Acting President Shelton Haynes and the RIOC Board of Directors:
Any statement from RIOC regarding status of Southpoint Park shoreline project and petition from Wildlife Freedom Foundation opposing it?

Assembly member Seawright signed the petition.

Any comment on charge that 325 trees will be destroyed

Will the project be delayed or is it still on schedule. When will work begin?

Acting RIOC President Shelton Haynes replied this evening:
The goal of the Roosevelt Island Southpoint Park project is to repair the erosion of the east and west seawalls and is critical to ensure the health and safety of the public while visiting Southpoint Park. The proposed plan was reviewed and approved by several federal, state, and local agencies charged with protecting the environment, including the U.S. Army Corps of Engineers (USACE), the U.S. Department of the Interior (DOI)– Fish and Wildlife Services, the National Marine Fisheries Services (NOAA), and the New York State Departmental of Environmental Conservation (NYSDEC). The RIOC Board of Directors unanimously approved the plan earlier this year.

Thursday, April 2, 2020

Roosevelt Island NY State Assembly Member Rebecca Seawright Shares Info On Federal Coronavirus Recovery Checks, Financial Assistance To Small Businesses Affected By Coronavirus And Answers Questions At Virtual Town Hall

Roosevelt Island's NY State Assembly Member Rebecca Seawright shares info on how to receive Federal Covid 19 recovery funds


and financial assistance available for small businesses affected by Covid 19

Assembly Member Seawright adds:

Wednesday, March 4, 2020

Roosevelt Island Southpoint Park Shoreline Reconstruction Project To Repair Decaying Seawall and Provide Public Access To Waterfront Draws Petition Opposing Project As Destroying Wildlife And Native Plant Habitats - RIOC Board Meeting Presentation Tomorrow Evening On Subject

The March 5 Roosevelt Island Operating Corp (RIOC) Board Of Directors meeting will include

1. Presentation Regarding Southpoint Park Project

According to RIOC:
... The Southpoint Park seawall is failing and in dire need of immediate repair. Furthermore, the soil between the shoreline and the steel fence is heavily contaminated and must be remediated once the seawall repair work begins. This is according to New York State Department of Environmental Conservation (NYS DEC) regulations. These two conditions must be addressed over the next year, meaning the area along the east and west shorelines of Southpoint Park will be disturbed anyway. Please note that work will not take place until after spawning season is over in July.

RIOC, in cooperation with our various state/federal partners at NYS DEC, FEMA and the Army Corps of Engineers, has decided to take this opportunity to improve both the natural habitat and pedestrian access to our Island’s beautiful riverfront. Remember, better waterfront access is a high priority for both New York City and New York State. The design featured in the Langan presentation will not permanently remove natural habitat. Nothing is being paved over. If anything, it will be better than before.....
A petition drive has been organized by some who oppose the Southpoint Park Shoreline Reconstruction project because they think it will destroy the existing wildlife habitat.

Roosevelt Island Southpoint Park Seawall Restoration/Pathway Project, Citibike Sharing Locations And Public Purpose Fund Allocations Among Items On Agenda For March 5 RIOC Board Of Directors Meeting - Ask Questions And Give Your Comments At Public Session Prior To Meeting

The Roosevelt Island Operating Corp (RIOC) Board of Directors will meet 5:30 PM Thursday, March 5 at the Cultural Center Theater (548 Main Street). You're invited to  attend,, ask questions and share concerns about Roosevelt Island during the opening Public Session before the start of the meeting. Sign up to speak here.

Among the items on the Agenda are:

A Southpoint Park Shoreline Restoration Project presentation (which has received objections from some community members who believe it will destroy the existing wildlife habitat),
 Agreement to install Citi Bike sharing docking stations for 72 bikes at 4 Roosevelt Island locations
and
Approval of Public Purpose Funds to Roosevelt Island Non-profit organization.

Thursday, February 28, 2019

Hey Susan - RIOC President Susan Rosenthal Answers Roosevelt Island Residents Questions On Dog Run Site Selection Safety, Tram Station Elevator, Motorgate Electric Car Charging Stations, Seawall Replacement, Sportspark Locker Rooms & More

Roosevelt Island Operating Corp (RIOC) President Susan Rosenthal answers your questions in this fifth installment of Hey Susan feature.


HEY SUSAN!

An occasional column of questions and answers to and from RIOC President and CEO Susan Rosenthal

HEY SUSAN!

I have a few concerns. There was considerable talk that the dog park would be moved to the area just south of 480 Main Street and adjacent to the sprinklers and playground. This area is already congested in the summer with considerable foot, bike, and RIOC vehicle traffic. Has there been a decision where the permanent home will be for the dog park and if 480 is that location, can you please reconsider?

Also, what is the hold up on the new tram station elevator? There has not been any progress for months on that site and the old elevator is breaking down more than ever. Is there a reason why they have not been working on it?

Lastly, the construction on the new Southtown building blocking the side walk is a traffic accident waiting to happen. The residents of 480 are forced to cross the street without a crosswalk and the view from both directions is limited for drivers and pedestrians. This paired with area driveways results in a lot of cars turning and people walking with no crosswalk. Can RIOC address this?


SUSAN: We chose the dog park location based upon the locations of other dog parks throughout NYC’s parks. The issues you raise can be handled with fencing, gate locations, and landscaping. Also, by locating the run there, we will have more open common space for all residents when Riverwalk buildings 8 and 9 are completed. Hudson-Related has shared some of their recreational ideas for that open space and it will be a great addition to the island. We have reviewed the issues you raised about the dog run with PSD (our Chief and Deputy have extraordinary experience in security and safety from their NYPD days) and they are confident that this location will not cause any unmanageable concerns.

Regarding the Manhattan Tram elevator, the construction drawings had to be revised because soil borings demonstrated a need to change the pile foundation design to support the structure. RIOC hired additional engineers to assist in the necessary modifications, which have been completed. We are now awaiting NYC Department of Buildings’ and NY Transit Authority approval, as well as the NYC Parks permit in order to proceed.

PSD was made aware of sidewalk safety issues around the new Southtown building construction and added signage for the protection of our pedestrians.


HEY SUSAN!

Any thoughts to providing charging stations for electric/hybrid cars in Motorgate? Electric cars are the future. Can you help by providing a means to help clean the air on Roosevelt Island?

SUSAN: Yes, we are doing more than thinking about charging stations! After the completion of the waterproofing project at Motorgate Garage, (we expect the project to be approved by the Board in April), we have plans for charging stations, new striping, and new signage. The current plan is for four charging stations, with the possibility of expanding to six.

HEY SUSAN!

Hopefully this $8.7 Million sea wall initiative has taken into consideration the rapidly rising sea level that came very close to taking RI out during storm Sandy?

SUSAN: The project you are referring to is for new seawall railings around the entire island. The seawall railing contractor has been repairing concrete damage on the face and topside of the seawall as they work northward. We also have a FEMA grant which is being used to repair an existing part of the seawall made of stone that was damaged in hurricane Irene.

We are in the midst of a seawall replacement project which will completely transform and beautify the east and west shorelines of Southpoint Park. The existing concrete retaining wall will be replaced by a “rip rap” revetment – basically, a sloping berm of armor stones that serve a similar purpose as a retaining wall, but is more cost effective to install and maintain, while allowing better access to the water. Along with the revetment, the project will remove the scrub brush along the existing seawall and replace it with professionally landscaped paths and seating for island residents and visitors. Once the scrub is removed in these areas, the views will be excellent and this area will become much more attractive as a destination for residents, especially in the warmer months.

We are continuing to evaluate the rest of the existing seawall to determine where replacement with a durable revetment is needed.

HEY SUSAN!

The men's locker room at the Sportspark pool has fallen into a state of disrepair. Issues include: handicap-access showerhead malfunctioning, one of the urinals malfunctioning, and the swimsuit-drying machine not working. This is on top of the chronic issues of: warped, dusty and rusting lockers, soap dispensers frequently empty, and a lack of anti-slip matting that make the wet floors a daily hazard for little wet feet. Thank you so much for your team's attention to this. I understand that a complete overhaul of the facility (while long overdue) would be a large investment. But routine plumbing repairs, some anti-slip mats, and closer attention to things like soap & paper towels would cost little and go a long way.

SUSAN: Thank you for reaching out regarding the locker rooms at Sportspark. We have a significant project addressing the bathrooms, locker rooms, HVAC system, and much more, which we intend to bring to the Board on March 7th in order to move forward with construction/design drawings.

We will address the other points you have raised with our maintenance staff. Thank you for bringing them to our attention.

Do you have a question you’d like to have answered by RIOC President & CEO Susan Rosenthal? Send it to the subject HEY SUSAN! at information@rioc.ny.gov. Want to report a problem? Send us feedback at rioc.ny.gov/Requesttracker.aspx.

Tuesday, January 8, 2019

Hey Susan, RIOC President Susan Rosenthal Answers Questions From Roosevelt Island Residents On Octagon BBQ Area Fencing, Unsafe Seawall Netting, Basketball Clinic, Sprinkler Fountains, Youth Center Building Renovation, Google Maps, Lighthouse Foot Bridges & Pedestrian Access To 59th Street Bridge

The Roosevelt Island Operating Corp (RIOC) has a recent new communication feature for residents, - Hey Susan - in which RIOC President Susan Rosenthal will answer questions you ask her.

Here's the fourth installment of Hey Susan.

HEY SUSAN! Please consider, fix and do something about (fill in the blank)
An occasional column of questions and answers to and from RIOC President and CEO Susan Rosenthal

A drawing of a face

Description generated with high confidenceHEY SUSAN! – I was wondering if the fences that were installed by the Octagon in April (and originally expected to be down by June) are now a permanent fixture?  One of the “curmudgeon bloggers” on the Island spoke with a worker at the end of October who said it would be gone in two weeks, yet here we are almost in December and the eyesore is still there. Additionally, is the fence preventing working from removing the large limbs that cracked during the early snowstorm and are now precariously hanging over picnic tables? Given how seriously RIOC has taken tree removal lately, this seems like it would be a priority.

SUSAN: You may have noticed, since last month, that the green tarps along the fence line of the project have been removed. As you may know the City’s Department of Environmental Protection built an access road along the path from Main Street to the Promenade. RIOC had no control of the timing and or pace toward completion of the construction. When we inquired and met with the DEP staff in December, we were informed the fencing will be removed once the sod has an opportunity to knit i.e. become firmly rooted along the road. The tarps’ removal was a compromise to provide better street lighting and visibility in the area. And rest assured, we’ll have any hanging or downed tree limbs removed before the fencing is removed and the area is open again to the public.

HEY SUSAN! When will the orange netting finally be replaced by the new metal railings along the river, between the subway and Island House? That stretch of the railings surely has more foot traffic, especially of children, than the stretch that has already been completed by Cornell, for example.
I cannot be the only parent who finds the planning and pace of the replacement of the railings unacceptably dangerous. In several places the orange netting is torn, leaving large gaps through which any young child could fall or hurt themselves. A more minor consideration is the toys, scooters etc. that could roll through those gaps and pollute the environment. 

With winter weather ahead, I am concerned that progress on finishing the replacement of the railings along that stretch appears to have stalled completely. I would be grateful for an update, not to mention some explanation behind the poor planning of removing existing railings many months before the replacement railings could be installed. 

Clearly the old railings would have been safer and more cost-effective and environmentally- friendly than plastic netting that rips. Many thanks in advance for your attention to these matters. 

SUSAN: I had my staff do a walk through and we found only one section of orange netting, near the Meditation Steps, that was ripped. We’ve asked the contractor to get that fixed today.

As you know, the long deteriorating Roosevelt Island seawall railings that run along the majority of the Island’s shoreline, about 3.5 miles in length, are being replaced with new anti-corrosive steel railings. The $8.7 million project is being completed by Elit Green Builders Corporation which so far has completed about half of the project. The work is on-going – removals and installations on the eastside and westside of the Island – depending on the weather (the concrete pours can only occur in dry weather at 40 degrees or higher) and when railings arrive from the foundry where they are being custom made. The work is expected to continue through the spring.


HEY SUSAN! Will there be a basketball clinic on Saturdays for kids over the winter?

SUSAN: Yes, we are finalizing the program schedule now. An announcement will be made shortly, and information can be found on our website at https://rioc.ny.gov/382/Youth-Center.

HEY SUSAN! I’ve asked this question before and you haven’t responded. What about better sprinkler systems for the children in summer heat? In such a nice neighborhood, there should be better sprinkler system for the kids to use in the summer time. Will improvements be made to the one by the baby park? Or, will one be added to the park across from the school? 

SUSAN: The spray fountain at Blackwell Park was turned off temporarily for a couple weeks during the summer for water testing and turned back on in August. It will be turned back on in the Spring once we begin using the irrigation system again. We haven’t received any complaints about its quality. What would you like to see improved? Also, there is no plan to add a spray fountain at Capobianco Field across from PS/IS 217.

We have installed new padded ground surfaces at both Blackwell and Al Lewis parks this summer. There will be additional improvements at Blackwell – more play equipment, improved seating at the courts etc. coming this year as well as new swings installed at Octagon Park.  As you can see, we are continuing to upgrade our parks for the greater enjoyment of all our families and children. Please continue to share your ideas as we move forward.

HEY SUSAN! Is there a new ETA on when the Youth Center will be moved back to 506 Main Street?
The last date I was told was November 6. I was then told it was pushed to the first week of December.
Is there a new time frame now? Moving the program back to Main Street doesn’t seem to be a priority the way it once seemed to be.

SUSAN: First, our existing program, temporarily located on the second floor of Sportspark, is doing great. Our original plan for 506 Main was just to complete a facelift. Once we got into and fully examined the building we realized more was needed to properly renovate the venue: cosmetically, structurally, ADA and code compliance. While there is no rush, the job should be completed by the end of 2019.

HEY SUSAN! Google Maps doesn’t provide efficient transit directions for Roosevelt Island when F train service is disrupted. It seems like Google doesn’t recognize the Tram or any trains that run on the F line (for example, the R train stopped in both directions on the F line this weekend when the F did not). 
There are over 11,000 residents of Roosevelt Island, we should be able to know how to get home from Manhattan or Queens during the weekend. Are you working with Google and MTA to fix this issue?

SUSAN: The MTA posts notices about the transportation alternatives for weekend travel to and from Roosevelt Island at the subway station and via their website at http://alert.mta.info/. We have no jurisdiction as to what they choose to do with Google. RIOC is now working with Google Transit to add Roosevelt Island Tram information of which we do have jurisdiction. Stay tuned for our announcement of its debut. Also have you tried using other transportation apps like Moovit? They seem to have accurate and useful up-to-date updates on all public transit outlets.

HEY SUSAN! Any projected completion date for the renovation of the two wooden footbridges near the lighthouse at the northern tip of the island? I haven't seen much progress. We love walking in Lighthouse Park. We sorely miss walking around the Lighthouse itself, which is inaccessible now and has been so for several months. What's up?

SUSAN: RIOC is working with Cameron Engineering for the renovation design drawing package of the two-foot bridges. These bridges have been fixed several times previously only to be washed out again by flooding. We hope to incorporate some long term structural and landscape solutions this time to prevent this from happening in the future. Currently, the project is in the design and permitting phase. The construction of the project is expected to finish by late spring of 2019.

HEY SUSAN! Has RIOC ever investigated the possibility of reinstating access for Roosevelt Island residents to the Queensboro bridge?  I recently came across some old news articles and found that RIRA made a presentation to Community Board 8 back in 2007 to try and convince them that – for multiple reasons, including safety, the growing Island population and strain on public transit and general connectivity – it was important to reinstate pedestrian access to the Queensboro bridge from Roosevelt Island. 

See http://uppergreenside.org/blog/2007/04/11/roosevelt-island-queensboro-bridge-access/.  CB8 unanimously approved RIRA’s proposal for conducting a feasibility study to physically connect Roosevelt Island to the Queensboro Bridge pedestrian and bike path, but the trail seems to end there.  A few online articles reflect that DOT did not seem to take the request seriously.

I understand that the bridge is under the City’s control.  That said: Would RIOC support residents in a push to raise this issue again at Community Board 8 and/or with the Department of Transport? 

The importance and utility of creating this link has only grown since 2007.  The Island population continues to grow.  Two new Riverwalk buildings are planned right next to the bridge.  We now have Cornell Tech.  A hotel is being constructed, and an Executive Education Center.  Amazon will be building its new HQ2 directly south of the bridge in Long Island City.  The ferry and Tram are great, but a walking link to Manhattan and LIC would be transformative for the Island (and frankly, they seem like a good idea from a safety/evacuation plan point of view). 

There are so many people and entities on the Island (including RIOC) that would benefit from this increased connectivity.  What can we as Roosevelt Island residents do to push this issue?  If RIRA were to raise this again, could it count on RIOC’s support?  Would RIOC be willing to play a role in bringing together representatives from Hudson Related and Cornell Tech to urge them to support this proposal? 

SUSAN: Yes, having such an elevator or stair connection to the 59th Street Bridge does seem to be a good idea in theory, but several feasibility studies have shown we don’t have the land area on the Island to build it. We would suggest that you contact City Council Member Ben Kallos’ office directly to inquire more about other current plans being discussed.

SUSAN: Thanks to you all for submitting your questions to HEY SUSAN! We look forward to more in the coming months. Wishing everyone a happy and healthy 2019!

Have a question for HEY SUSAN!? Submit it to Ms. Rosenthal at information@rioc.ny.gov.

Thursday, June 21, 2018

RIOC Updates On Roosevelt Island Infrastructure Repair Projects - Helix Ramp, Tram Station Platform, Tram Elevators, Seawall, Blackwell House & Playgrounds

Roosevelt Island Operating Corp (RIOC) Public Information Officer Alonza Robertson updates us on current Roosevelt Island infrastructure projects. According to Mr. Robertson:

There is very little available, or unaccounted for, space left on Roosevelt Island’s 147 acres to build new infrastructure. But there’s a big need to maintain its existing infrastructure and keep it updated for the next 50 years.

The reality though is RI’s infrastructure maintenance is often costly, time-consuming and considered a disruptive inconvenience to residents, business owners and even tourists and visitors who live, work and flock here in growing annual numbers. But the Roosevelt Island Operating Corp (RIOC) believes maintenance’s long-term benefits trump the short-term inconveniences

Last year, RIOC embarked on a robust five-year capital improvement plan. Some of those initial projects now are close to completion. Below, we’ll update the status of those, revisit the progress of others and maybe introduce you to more plans of which you might have been unaware.


The Helix Ramp: This road construction repair job began in February and during early demolition and preparation the structure was found to be in a more severe state of disrepair than previously thought. In May, the contractors and project managers extended the project scope and timeline for completion. The two-lane spiral roadway and adjacent plaza will now re-open to traffic on July 3. There will be intermittent disruptions to two way traffic to complete installation of new guardrails as well as expansion joint material along the lower ramp of the helix.


The deteriorating Roosevelt Island seawall railings that run along the majority of the Island’s shoreline about 3.5 miles in length are being replaced with new anti-corrosive steel railings. The $8.7 million project is being completed by Elit Green Builders Corporation which so far has completed about a third of the project around the southern end of the Island. Work is expected to continue through December 2018.

The Tram Station platform construction, a project that began May 16 and was scheduled to last 30 days, has been delayed by inclement weather. The construction work along with the re-installation of MetroCard vending machines should be completed by the end of June. Both cabins of the Tram will return to service at that time.

Tram Station Elevator: A $6.1 million construction project to upgrade the Manhattan Tram Station elevator started this week and the two building phases will be finished by late Spring 2019. The elevator project, at 59th Street and Second Avenue, calls for an iconic, two-bank, ADA-compliant glass elevator which replaces the existing elevator that has outlasted its expected mechanical life.

The RI Youth Center renovation work is now in the proposal bid process. Once a contractor is selected this summer, the work will last up to three months. The youth center programs will be relocated to the Sportspark during the construction period.

Blackwell House Renovation is a full structural refurbishment of the original farmhouse home of the Blackwell family, one of the early owners and inhabitants of what is now known as Roosevelt Island. The outside porch and entire interior, of the home built in 1796, has been totally gutted and new floors, walls, support beams, stairways, and code-compliant HAVC systems are being installed. The house will serve as a community meeting facility and new office for the Roosevelt Island Historical Society and reservoir for all Island and RIOC archives. Current completion date is early fall 2018.

The Al Lewis and Blackwell north playground areas will be getting playground equipment repairs and replacement and new poured in place rubberized play surfaces; work is set to begin later this summer.

Stay tuned for additional updates and news about upcoming projects at Octagon Field, Firefighter’s Field, Motorgate, Southpoint Park and Lighthouse Park.

Monday, April 2, 2018

Resident Asks RIOC Not To Mar View Of East River Waterfront From Roosevelt Island Pier With A Royal Flush Porta Potty

Roosevelt Island resident Adina Grunn reports:

As you can see this porta-potty placement is extremely unfortunate.


 I doubt it was deliberately placed to mar the view over Eleanor’s Pier.


So, could you please ask Royal Flush to move this unit close to the end of the sea-walk (perhaps by the Starbucks garbage enclosure). I’m sure a dire need for Royal Flush could definitely be addressed by walking a quick couple of yards south.
Roosevelt Island Operating Corp (RIOC) Public Information Officer Alonza Robetson replies:
Thank you for forwarding your reader's question. The portasans belongs to our seawall railings contractor who dropped the unit off Friday in preparation for work in that area. Back on site today, after the weekend, the contractor moved the portasans inside the barricades of their approved work area at the Southtown West location.

Tuesday, February 20, 2018

Roosevelt Island Youth Center Contract And Seawall Repair Negotiations On Agenda For Executive Session At RIOC Operations Advisory Committee Meeting February 27 - Gallery RIVAA Public Purpose Funds Modification In Public Session

The Roosevelt Island Operating Corp (RIOC) Operations Advisory Committee will meet Tuesday, February 27. Among the items on the Agenda is the Youth Center Operator Contract
 


 The discussion will be held in Executive Session closed to the public. The seawall railing item will also be held in Executive Session.

According to RIOC:
PLEASE TAKE NOTICE that a meeting of the Operations Advisory Committee Meeting of the RIOC Board of Directors will be held on Tuesday, February 27, 2018 at 5:30 P.M. at the RIOC Administrative Office, 591 Main Street, Roosevelt Island, New York.

Agenda:

1. Discussion of Modification of Public Purpose Fund Grant to RIVAA Gallery.

Chair’s Motion for Executive Session to Discuss:
Legal Matters in Connection with the Youth Center Operator Contract Award
Seawall Repair Negotiations.
According to the NY State Open Meetings Law:
§100. Legislative declaration.

It is essential to the maintenance of a democratic society that the public business be performed in an open and public manner and that the citizens of this state be fully aware of and able to observe the performance of public officials and attend and listen to the deliberations and decisions that go into the making of public policy. The people must be able to remain informed if they are to retain control over those who are their public servants. It is the only climate under which the commonweal will prosper and enable the governmental process to operate for the benefit of those who created it....
... §103. Open meetings and executive sessions.
(a) Every meeting of a public body shall be open to the general public, except that an executive session of such body may be called and business transacted thereat in accordance with section one hundred five of this article....
... §105. Conduct of executive sessions.
1. Upon a majority vote of its total membership, taken in an open meeting pursuant to a motion identifying the general area or areas of the subject or subjects to be considered, a public body may conduct an executive session for the below enumerated purposes only, provided, however, that no action by formal vote shall be taken to appropriate public moneys:
a. matters which will imperil the public safety if disclosed;
b. any matter which may disclose the identity of a law enforcement agent or informer;
c. information relating to current or future investigation or prosecution of a criminal offense which would imperil effective law enforcement if disclosed;
d. discussions regarding proposed, pending or current litigation;
e. collective negotiations pursuant to article fourteen of the civil service law;
f. the medical, financial, credit or employment history of a particular person or corporation, or matters leading to the appointment, employment, promotion, demotion, discipline, suspension, dismissal or removal of a particular person or corporation;
g. the preparation, grading or administration of examinations; and
h. the proposed acquisition, sale or lease of real property or the proposed acquisition of securities, or sale or exchange of securities held by such public body, but only when publicity would substantially affect the value thereof.
2. Attendance at an executive session shall be permitted to any member of the public body and any other persons authorized by the public body....
UPDATE 2/26 - According to RIOC:
PLEASE TAKE NOTICE that a meeting of the Operations Advisory Committee Meeting of the RIOC Board of Directors will be held on Tuesday, February 27, 2018 at 5:30 P.M. at the RIOC Warehouse, 680 Main Street, Roosevelt Island, New York.

Wednesday, February 14, 2018

RIOC Seeking Owners Rep Consultant To Help With $33 Million Roosevelt Island Capital Improvement & Maintenance Projects Planned For Next 2 Years - Dad Asks RIOC To Start Improvements With Blackwell Park Sandbox

The Roosevelt Island Operating Corp (RIOC) is about to begin 24 months of major infrastructure and maintenance projects.

Image Of Broken Seawall Railing Near Octagon Building From December 2017

According to RIOC Public Information Officer Alonza Robertson:
The Roosevelt Island Operating Corporation has an ambitious and aggressive $33 million plan to complete more than 30 capital improvement and maintenance projects during the next 12-24 months. These include the Helix repair, seawall railing replacements, bike ramp and lane construction, elevator and potential escalator repairs, Youth Center and SportsPark renovations, sidewalk, playing fields and playground improvements among others.

The projects are all in varying stages of concept, design and construction. RIOC's in-house project management team will be at capacity once two new full-time project managers and the Director of Asset Management come aboard later this month. But even with the new hires, additional resources will be required to achieve our goals. After careful evaluation, RIOC has decided to utilize consultants - via the recent RFP for Owner’s Representative Services for Capital Projects & Strategic Planning - to support the current demands for the following reasons:
  1. RIOC anticipates that the workload will fluctuate significantly and staffing up for a peak demand will leave us with excess staff during low periods. A consultant will be able to accommodate this fluctuation and RIOC will benefit by only paying for the additional resources when they are required.
  2. RIOC has a demand for proven consultants in managing multi-disciplined projects through design, regulatory and construction processes. Not all of RIOC’s planned projects require full-time consultants daily but they will require full-time involvement of specialists at varying intervals throughout each of the projects being considered.
  3. The Owner’s Representative would assist in the regulatory process with private and public agencies, take an active role in the Design Process for projects, prepare and evaluate bid proposals, perform inspections, contract administration, and other related activities.
  4. RIOC will benefit from the experience of the organizations or firms who have successfully completed similar projects throughout NYC.
RIOC is looking at the Owners Representative role as an extension of our existing team. We have no intention of reducing staffing, rather we are bolstering and supplementing our existing team to prepare for the increase volume of projects that are being undertaken.
Here's the RIOC Owners Rep for Capital Planning & Projects RFP.

During the February 7 Roosevelt Island Residents Association (RIRA) Common Council meeting Public Session, a Roosevelt Island Dad asked RIRA to support a request that RIOC make improvements to the Sandbox in Blackwell Park.


According to the Roosevelt Island Dad:
... The Sandbox is in disrepair for some time....
And:
... The level of sand has dwindled to an inch or so and the bottom tarp that is underneath the sandbox is visible.

Admittedly, there is no glass or hazards in it but it's not pleasant to be in.

I'd like to ask this group to support an idea of having it topped off with sand once a season....

... My request is that from time to time a dump truck of sand backs up and dumps a load of sand in the sandbox...



RIOC does not need an Owners Rep to help fix the Blackwell Park sandbox.

UPDATE 2/15:
According to RIOC, the sandbox will be removed as part of an upgrade to the Blackwell Park playground equipment this spring. There will be no sandbox replacement.

Monday, December 18, 2017

RIOC Budget Approval, Public Purpose Funds Authorization & Funds For Youth Center Program Among Items On Agenda For December 19 Roosevelt Island Operating Corp Board Of Directors Meeting

The Roosevelt Island Operating Corp (RIOC) Board of Directors will meet 5:30 PM Tuesday, December 19 at the Cultural Center (548 Main Street). Among the items on the Agenda are

Prior to the start of the RIOC Board meeting, there will be a public comment period. Sign up here to speak at the meeting.

The RIOC Proposed Budget reports rescheduling the start of Southtown Building 8 and 9 construction to April 2018 and July 2019 respectively.

The RIOC Budget also includes projected payment of over $23 million from NY State for the Cornell Tech project.

Image From RIOC

According to the Proposed RIOC Budget for Fiscal Year 2018-19 (Page 1):
Revenues

RIOC’s Proposed Budget FY 2018‐19 projects revenues of $51,203,000 a increase of $23,234,000 or 83.07 % over the Approved Budget FY 2017‐18 amount of $27,969,000. RIOC generates most of its revenues from long‐term ground leases to developers of housing projects on the Island. These leases specify the manner in which the ground lease revenues are derived, including amounts, timing, and escalation of ground lease payments, specifically residential fees, ground rents, and public safety fees. In addition, RIOC generates revenues from its Tramway transportation system, Motorgate parking garage, metered street parking, commercial leases, interest income, and other revenues. Other revenues mostly consist of permitting fees collected for activities that take place in the Sportspark sports facility, the Cultural Center, the Sports Fields, and third party construction on the Island.

Residential fees are projected to decrease by $534,000 or 26.47%. This is mainly due to two factors: (1) the rescheduling of the projected construction dates for Southtown Building 8 and 9 to April 2018 and July 2019; respectively, resulting in the deferral of Tax Equivalent Payments in the amount of $268,000 to the respective fiscal periods, and (2) the completion of the Island House Initial Sponsor Sales in FY 17‐ 18, resulting in the reduction of the projections for coop and condo sales transactions fees for FY 18‐19 in the amount of $221,000.

Ground rents are projected to increase by $23,541,000 or 194.17% due to the projected payment of the State’s contribution for Cornell. Furthermore, projections for Rivercross and Westview are based on current levels, however both projected ground rents are expected to increase.

Commercial rents are projected to decrease due to the cost for the joint marketing campaign between RIOC and Hudson Related Retail LLC.

Tramway revenues are projected to decrease by $233,000 or 4.08%, due to over‐projection of the revenues in the FY 17‐18 budget.

Public Safety revenues are projected to increase by $56,000 or 2.86% due to contractual escalations. Transport/parking revenues are projected to increase by $510,000 or 19.28%, mainly due to the addition of 15 additional parking meters on the Island.

Interest revenues are projected to increase by $35,000 or 33.02% due to gradual increases in interest rates.

Other Revenues is projected to decrease by $98,000 or 5.48%. Most of the decrease is due to the provision of free usage of the Sports Fields to meet the recreation needs of the community residents.
Also (Page 4-5):

Monday, August 14, 2017

NYPD Harbor Patrol Arrest Kayaker Spray Painting Graffiti On Rocks Near Roosevelt Island Bridge

The Roosevelt Island Twitterverse reports:

Tuesday, August 8, 2017

Roosevelt Island Ferry Service Presentation, Seawall, Playground & Basketball Court Repair Among Agenda Items For August 9 RIOC Directors Board Meeting - New Red Buses & Tramway Platform Equipment Relocation Too

An August 9 Special Meeting of the Roosevelt Island Operating Corp (RIOC) Board of Directors will take place August 9 starting 5:30 pm at the Cultural Center (548 Main Street).

 

Prior to the start of the RIOC Board meeting, there will be a public comment period. Sign up here to speak at the meeting.

Among the items on the Agenda are:
Seawall Railing Construction and Design Services,

Al Lewis and Blackwell Park Playground Flooring Replacement,


Resurface Capobianco Field Basketball Court


MTA Tramway Equipment Relocation 

New Red Buses

Tramway Station Renovations and

 Roosevelt Island Ferry Service Presentation NYC Ferry Operator Hornblower.
According to RIOC:

Wednesday, June 21, 2017

Roosevelt Island Blackwell House Renovation, Seawall Railings & New Red Buses On Agenda For June 21 RIOC Board Of Directors Meeting Tonight - Public Comment Session Prior To Start Of Board Meeting Too

The June 21 Roosevelt Island Operating Corp (RIOC) Board of Directors will take place starting 5:30 pm  tonight at the Cultural Center (548 Main Street).

 Image Of RIOC Board Of Directors Meeting

Prior to the start of the RIOC Board meeting, there will be a public comment period. Sign up here to speak at the meeting.

Among the items on the Agenda are:
Below is the full Agenda:
AGENDA

JUNE 21, 2017 MEETING OF

THE ROOSEVELT ISLAND OPERATING CORPORATION BOARD OF DIRECTORS

THE CULTURAL CENTER THEATER, 548 MAIN STREET,

ROOSEVELT ISLAND, NEW YORK

5:30 P.M.[1]

I. Call to Order

II. Roll Call

III. Approval of Minutes

1. May 25, 2017 Board Meeting (Board Action Required)

IV. Old Business

New Business

1. Presentation of RIOC's Audited Financial Statements for Fiscal Year Ending March 31, 2017

2. Approval of Annual Report for Fiscal Year Ending March 31, 2017 (Board Action Required)

3. Approval of Report on Procurement Contracts for Fiscal Year Ending March 31, 2017 (Board Action Required)

4. Approval of Report on Investments for Fiscal Year Ending March 31, 2017 (Board Action Required)

5. Approval of Property Report for Fiscal Year Ending March 31, 2017 (Board Action Required)

6. Authorization to Enter into Contract with AFL Construction Co. Inc. for Blackwell House Interior and Ramp Way Renovations (Board Action Required)

7. Authorization to Amend the Contract with Elan Engineering, LLC for Seawall Railing Design and Consulting Services (Board Action Required – Materials to Follow)

8. Authorization to Enter into Contract with New Flyer Industries, Inc. for the Purchase of Two Diesel Buses (Board Action Required)

9. Authorization to Enter into Contract with Thomson Reuters for Access to On-Line Westlaw Legal Research Libraries (Board Action Required)

10. Approval of Extension of the FY 2016-17 Public Purpose Grants Period (Board Action Required)

11. President’s Report

12. Committee Reports

a. Audit Committee

b. Governance Committee

c. Operations Advisory Committee

d. Real Estate Development Advisory Committee

13. Public Safety Report

VI. Adjournment

1] The RIOC Board Meeting will commence following a public comment period. The public comment period is not part of the meeting.
According to RIOC memo in support of the Blackwell House renovations Agenda Item:
In 2014, the Board authorized RIOC to extend the contract with consultants, Saratoga Associates (“SA”), to proceed with coordination and re-filing of project documents for the Blackwell House Interior Restoration Project. SA completed its pre-construction services and the construction documents were approved by the NYC DOB for a contractor to obtain the required permits.

This project is partly funded by the New York City Department of Cultural Affairs (DCA) through a grant to the Roosevelt Island Historical Society in the amount of $364,000.00. At the conclusion of negotiations, the DCA/RIOC contract was registered on October 24, 2016, thus paving the way for the construction works to commence.
The scope of work consists of: demolition of the interior of the building; installation of new partitions, ceilings, doors, staircase and repairs to flooring; installation of new mechanical, electrical and plumbing systems; installation of a new ADA access ramp; repairs to the deteriorated porches....

... RIOC hereby recommends that a contract be awarded to AFL
Construction Co. Inc. for the Blackwell House Interior Restoration and Access Ramp Project for the sum of $1,465,200.00, with a 25% contingency of $366,300.00. The total project cost is $1,831,500.00. The duration of this project is 270 calendar days....
According to the RIOC memo in support of Public Purpose Grant period extended:
... Extensions of the FY 16-17 PPF Grants are requested for the following three (3) grantees:

1. Main Street Theatre and Dance Alliance (“MSTDA”) – The grantee has completed its expenditures for scholarships, and some community programs for which PPF funds were requested. The grantee has requested an extension to hold some of the community programming over the summer of 2017, due to the scheduling needs of community organizations that will benefit from the programming. Therefore, an extension is requested to allow for this critical portion of MSTDA’s request to be performed during summer 2017, and for MSTDA to submit the corresponding documentation to RIOC.

2. PS/IS 217 Parent-Teacher Association (“PTA”) – The Salvadori Center has provided the programming for which PPF funds were requested. Some of the services performed by the provider took place during the school’s spring semester and the check to cover these funds was written after March 31, 2017. Therefore, an extension is requested so that the appropriate records may be submitted by PTA and accepted by RIOC.

3. Life Frames – Life Frames has completed the services for which the PPF funds were requested. However, a de minimis portion of the services (and corresponding expenses) were performed after the period of performance end of March 31, 2017. Therefore, an extension is requested so that the appropriate records may be submitted by Life Frames and accepted by RIOC.

The Public Purpose Grants are critical to programming and projects that benefit the community. Based on the foregoing, the extensions are requested through September 30, 2017, which should provide sufficient time for the remaining expenses to be incurred, submitted, and accepted.

Monday, April 24, 2017

Roosevelt Island Community Report From RIOC President Susan Rosenthal - RI Bridge Bike Ramp, Sportspark Pool, Seawall Railing, Tram Station Elevators, Motorgate Waterproofing, NYPD 114 Community Policing & More

Roosevelt Island Operating Corp (RIOC) President Susan Rosenthal reported to the April 20 RIOC Board of Directors meeting (Video web cast here) on current projects including:

Friday, March 24, 2017

Roosevelt Island Community Report From RIOC President Susan Rosenthal - Seawall Railings, Sportspark Opening Soon Maybe, Blackwell House, Tram Platforms & Elevators, Youth Center Rats, Renovation, Operator, Renwick Ruins, Water Safety, Picnic Tables, Water Fountains & BBQ's

Roosevelt Island Operating Corp (RIOC) President Susan Rosenthal reported to the March 23 RIOC Board of Directors meeting on current projects including:

  • Seawall railings replacement - start construction in June,
  • Sportspark announcement regarding opening hopefully by Monday or Tuesday,
  • Blackwell House renovation Request For Proposal (RFP) posted,
  • Tram Platforms renovation (both Manhattan and Roosevelt Island stations)
  • Rat problems at Roosevelt Island Youth Center,
  • Youth Center Building Renovation,
  • Youth Center Operator RFP being revised with assistance of NY State Office of Children & Family Services,
  • Renwick Ruins Scaffolding To Repair Falling Cornice and 
  • Final Report coming soon on status of Renwick Ruins condition commissioned by FDR Park (estimated cost of stabilizing Ruins is $20 Million)
Here's Ms. Rosenthal's report to the RIOC Board (Part 1)



Part 2:
  • Tram Elevator RFP - creating glossy brochures and exploring personal contacts seeking contractors,
  • Roosevelt Island Public Space Water - It's safe,
  • New BBQ's, picnic tables and benches, and water fountains,
  • Motorgate Gallery Art Gallery Opening and
  • Renwick Ruins Stabilization and future plans for re-purposing.

Tuesday, April 14, 2015

Fixing Roosevelt Island Seawall Railings, Upcoming Main Street Construction And Current Projects Review Among Items On RIOC Operations Committee Meeting Agenda For April 15

The Roosevelt Island Operating Corp (RIOC) Operations Advisory Committee is meeting tomorrow. Among the items on the meeting agenda are a discussion of the seawall railings


and upcoming Main Street Construction.

 Image of Recent Main Street Z Brick Replacement

According to RIOC:
PLEASE TAKE NOTICE that a meeting of the Operations Advisory Committee of the RIOC Board of Directors will be held on Wednesday, April 15, 2015 at 5:30 p.m. at the RIOC administrative office, 591 Main Street, Roosevelt Island, New York.

AGENDA:

Review of Current Projects
Discussion of Seawall Railings
Discussion of Operational Issues Related to Upcoming Main Street Construction
Any Other Committee Business That May be Brought Before the Committee

***

The Open Meetings Law of the State of New York requires that all public bodies conduct meetings, convened for the purpose of officially conducting public business, in a manner open to attendance by the general public to observe and listen.
Here's a discussion of necessary Roosevelt Island seawall improvements by RIOC President Charlene Indelicato and RIOC Director David Kraut during October 22, 2014 RIOC Audit Committee meeting on RIOC's Proposed 2015-16 Fiscal Year budget.



An audio web cast of the meeting will be available soon after the meeting.

UPDATE 4/16 - Audio web cast of meeting is here.