Thursday, January 17, 2019

Major Roosevelt Island Tram Overhaul To Begin 2nd Week Of February, Only 1 Tram Cabin In Service For At Least 10 Weeks Says RIOC - MTA Says No Disruption In Weekend Roosevelt Island F Train Service Thru April 19

This is not going to be fun. Be prepared for Roosevelt Island Tram service disruption starting second week of February. According to this announcement today from the Roosevelt Island Operating Corp (RIOC):

The Roosevelt Island Tram is scheduled to undergo two major maintenance projects that will reduce operating service to one cabin only beginning the second week of February and continuing for at least 10 weeks, the Roosevelt Island Operating Corporation (RIOC) announced Thursday.

Track cable relocation, phase 1 of the work, is a safety requirement of the American National Standards Institute (ANSI) for aerial tramways and gondolas operating in the United States.



As per the safety regulations (ANSI B77.1), the Tram is required to relocate its track cables after a pre-determined amount of time. RIOC’s Tram contractor Leitner-Poma, who totally rebuilt the Tram’s infrastructure nine years ago, will perform the work.

The timeline is subject to change depending on weather conditions and the conditions found within the equipment during the relocation. During that time, one cabin will be taken out of service, starting with the North cabin.

“Much like a car that has recommended maintenance at pre-determined intervals, we are that point with the Roosevelt Island Tram,” said RIOC CEO and President Susan Rosenthal.

“We apologize in advance for the inconvenience this may cause. But this effort is to create the safest transportation system possible and to extend its service life into the future,” Rosenthal said of the Tram that since 2016 has transported more than 10 million commuters. “We appreciate your patience and assistance with this important maintenance project.”

Track cables are basically the “road” that the Tram cabin runs on. Each track cable does have movement with every trip of the tram to allow for expansion and contraction, but for the most part the cables are fixed in a single location on each tower. Over time, this location is subject to more wear and bending actions than the other locations, which is the reason the cable is periodically relocated.

Each track cable also contains fiber optic lines inside the core which the Tram uses for communications and controls. This fiber optic line must be cut and re-terminated following the track relocation.

There will be periods of shutdown for both cabin systems during the actual movement of the rope, during tensioning and during the fiber optic changeover, but the plan is to conduct this work late at night and during normal overnight shutdown periods.

Leitner-Poma crews will be working seven days per week to complete the work as quickly as possible.

The second phase of work consists of four gearbox overhauls (inspecting and replacing internal parts such as the gears, bearings, seals and oil changes). This work will start as soon as Phase 1’s track cable relocation is complete. The schedule may change depending on the construction of needed parts and the impact of the federal government shutdown of the overseas import of those parts.

The duration of Phase 2 is estimated to last four to six weeks. During that repair, the Tram will be running daily on a one-cabin reduced capacity.

WHY ARE GEARBOX OVERHAULS NEEDED?

Each cabin is pulled by an assembly of two gearboxes. Due to the age of the gearboxes and following the gearbox failure on the North tram last August, Kissling AG, the original gearbox manufacturer and a leader in the industry, has recommended to proceed right away with the overhaul of all four gearboxes.

To help facilitate Island residents’ commutes during this period, RIOC will operate Red Bus shuttles between 59th-Street-and- Second-Avenue in Midtown Manhattan and Roosevelt Island during the weekday afternoon peak commute. Exact schedules will be released before the repairs begin.

In discussions this week with the Metropolitan Transportation Authority, which operates the New York City subway and bus system, RIOC officials received assurances that there will be no disruptions to the subway’s F Train line that services Roosevelt Island, including weekends through April 19.

Additional service will be provided via the E Train line, weeknights March 18 – March 22 and March 25 – March 29; and all four weekends March 23 – April 25.

RIOC has also asked NYC Ferry officials to consider expanding ferry service – to and from Roosevelt Island, Queens and Manhattan - during the weekday peak periods and weekends; and is awaiting their response.

More information about this project, updated Red Bus shuttle schedules and project timelines will be posted at rioc.ny.gov. Please forward additional questions or inquiries to RIOC’s Public Information Officer Alonza Robertson at alonza.robertson@rioc.ny.gov.
The Roosevelt Island Residents Association (RIRA) Common Council discussed the Tram service disruption during its January 9 meeting. Here's the discussion initiated by new Common Council member Justin Ellis looking for ideas to improve transportation options during the Tram service outage.



Remember what it was like last summer when only one Tram Cabin was in operation during the Tram Station Platform renovations.


Hopefully, the Tram tourist crowds will be less this winter than last summer.

UPDATE 4;30 PM - RIOC adds:
Why Offer the Red Bus Shuttle During the Afternoon Rush Only?

Some people has asked us about running the shuttle during the morning hours too. Our Transportation Department has found that due to morning rush-hour vehicle the free shuttle can only make two roundtrips trips (which equates to about 68 seated passengers) from Roosevelt Island to Manhattan via the 59th Street Bridge. That’s not an efficient use of resources.

As a transportation alternative, the Q102 MTA bus makes the route to Roosevelt Island every 20 minutes and takes riders directly to Queens Plaza where they are able to make transfer connections to three different train lines and two other buses headed directly to Manhattan.

In the afternoon, the shuttle can make up to five roundtrips from Midtown Manhattan. We hope that Roosevelt Island seniors, individuals with disabilities or in wheelchairs, and parents or caregivers with young children (strollers etc.) will use the service in addition to all else needing a ride.

Also, please note that though the Tram will be operating on a one-cabin basis, it will “load and go” to make as many trips as possible during peak times to decrease wait times. When we have two operational cabins, we typically wait until actual departure schedule times (no matter if we were full or had small amounts of passengers).

Friday, December 2, 2016

No Roosevelt Island F Train Service From Manhattan This Weekend And Next 2 But Roosevelt Island Tram Service Returns To Normal With Both Cabins Operating Starting December 3

First the bad news.

 Image From MTA

According to the MTA:
F Jamaica-bound trains are rerouted via the E after 47-50 Sts to Roosevelt Av

Weekends, 11:45 PM Fri to 5 AM Mon, Dec 2 - 5 • Dec 9 - 12 • Dec 16 - 19

No Jamaica-bound service at 57 St, Lexington Av/63 St, Roosevelt Island and 21 St-Queensbridge.
Now the good news. Both Roosevelt Island Tram cabins will be in service starting tomorrow. Hopefully, the long lines will be gone.


According to the Roosevelt Island Operating Corp (RIOC):
Please be aware that, on Saturday, December 3rd, the Tramway is scheduled to return to its regular service schedule, utilizing both Tram cabins.

Please note the last Red Bus shuttle from the Tram to Manhattan will be on Friday, December 2nd at 8 PM, and the last shuttle from Manhattan will be at 8:30 PM Friday.

Thank you for your patience during this necessary work.

Friday, November 4, 2016

Good News, Roosevelt Island F Train Service To And From Manhattan This Weekend Says MTA - No Planned F Train Service Disruptions For Rest Of Month During Tram Service Reduction Says RIOC

According to the MTA Weekender, there will be Roosevelt Island F train service


 to and from Manhattan this weekend.

Also, as reported yesterday, the Roosevelt Island Operating Corp (RIOC) reports that only 1 Roosevelt Island Tram Cabin will be operating for the month of November starting Monday, November 7, and:
... The MTA has advised that there are no planned F train service disruptions during this period....

Thursday, November 3, 2016

Roosevelt Island Tram Service Disruptions Starting November 7 - Only 1Tram Cabin Operating At A Time For Rest Of Month Due To RequiredInspections And Maintenance

Oh boy. This is not going to be fun.

According to the Roosevelt Island Operating Corp (RIOC):

Leitner-Poma, operator of the Roosevelt Island Tramway, has advised that, due to required inspections and maintenance on both Tram cabins (including the replacement of both cabin floors), the Tram will operate with one cabin, running on a peak schedule during the month of November. During this time, the Red Bus will provide supplemental service to Manhattan Monday - Friday from 10 AM to 8:30 PM, with buses departing every hour from Roosevelt Island to Manhattan and every half hour from Manhattan back to Roosevelt Island. These changes will take effect on Monday, November 7th .

The MTA has advised that there are no planned F train service disruptions during this period.

Thank you in advance for your patience during this necessary work
Plan for a very crowded ride on the Tram


starting


Monday November 7.

Is there anything RIOC can do to reduce the overcrowding of the Tram that is sure to result from only one cabin in use during this time?

Perhaps RIOC can consider eliminating weekend 5 & 10 K race permits and playing field permits for non-resident groups during the time only one Tram Cabin is in service in order to reduce Tram crowding. Find a way to discourage the tourists too.

UPDATE 11/4 - From RIOC:

Wednesday, July 23, 2014

Only One Roosevelt Island Tram Cabin Operational From July 28 - August 8 Says RIOC -Tram Operator Leitner Poma Conducting Safety Inspections During At That Time - UPDATE, Both Tram Cabins Running During Weekend Says RIOC


According to the Roosevelt Island Operating Corp (RIOC)
Leitner-Poma, operator of the Roosevelt Island Tramway, has advised that both Tram cabins will be undergoing a comprehensive safety inspection from Monday, July 28th until Friday, August 8th. During this time, one Tram cabin will be operational and will provide service every 7.5 minutes alternately from each station from 6 AM - 2 AM.

Thank you for your patience during this necessary work.

Sincerely,

Roosevelt Island Operating Corp Advisories Group
Expect a crowded Tram Cabin, particularly on the weekend if there is no F Train service in one direction.

UPDATE 7/24 - RIOC adds:
Leitner-Poma, operator of the Roosevelt Island Tramway, has advised that both Tram cabins will be undergoing a comprehensive safety inspection from Monday, July 28th until Friday, August 8th. During the inspection, the Tram schedule will be as follows:

Monday, July 28th to Friday, August 1st

Tram service will be provided with one cabin providing service every 7.5 minutes alternately from each station from 6 AM- 2 AM.

Saturday, August 2nd & Sunday, August 3rd

The tram will resume service with both cabins. During this time, rush hour service will be provided every 7.5 minutes from 7 AM to 10 PM.

Monday, August 4th to Friday, August 8th

Tram service will be provided with one cabin providing service every 7.5 minutes alternately from each station from 6 AM- 2 AM.

Saturday, August 9th, 06:00 AM The tram will resume service with both cabins.

For more information, please call 212-832-4559.

Thank you for your patience during this necessary work.

Sincerely,

Roosevelt Island Operating Corp Advisories Group
and Leitner - Poma explains the reason for the safety inspection.
LEITNER‐POMA OF AMERICA, INC.

2014 ‐ ROOSEVELT ISLAND AERIAL TRAMWAY INSPECTION

Arial transportation systems require systematic inspection routines. Roosevelt Island Arial Tramway is a state of the art ropeway transportation system used for mass transportation in an urban environment. It is subject to New York State licensing and inspection process. In addition the tramways manufacture requires multiple layered inspection routines. Inspections and testing are done on a daily, weekly and monthly basis to assure safe and reliable service. A staff of approximately 25 members is employed using New York City based individuals. This staff is charged with the responsibilities of daily operation and maintenance. Most of the inspections and testing are accomplished by them.

However, higher level inspections and testing are performed to assure the design and engineering integrity are maintained. These inspections are performed by engineers, factory personnel and the local staff. These tests are complex and require longer periods of time than allowed during the normal shutdown.

The tram schedule during the inspection will be as follows;
Monday. July 28th. To Friday August 1st.... Tram service will be provided with one single cabin.
Saturday. August 2nd. And Sunday. August 3rd... The tram will resume service with both cabins.
Monday. August 4th. To Friday. August 8th... Tram service will be provided with one single cabin.
Saturday. August 9th. 06:00 AM... The tram will resume service with both cabins.

We appreciate your cooperation and understanding. Leitner‐ Poma of America

Roosevelt Island Aerial Tramway – Operators.

Monday, June 3, 2013

No Roosevelt Island Tram Service Tomorrow Night 10 PM Thru 6 AM For System Upgrades Says RIOC - Will Tram Cooling System Be Part Of Upgrade?

According to the Roosevelt Island Operating Corp (RIOC)

Reminder:

Please be advised on Tuesday, June 4th 2013, both Tram cabins will be out of service beginning at 10 PM due to routine scheduled system upgrades. The Tram will resume normal service on Wednesday, June 5th at 6 AM.

Sincerely,

Roosevelt Island Operating Corp Advisories Group
Anybody think a cooling system for the Tram

 (Tram Station Windows Open Providing Breeze During Hot Weather)

during the hot summer months is part of the system upgrade?

One resident notes from a previous post on the hot tram:
 the tram has always been Hot now that the hipsters are here paying big rents.its a issue. Really
which was answered by another:
You keep using words like Yuppie and Hipster, but I don't think you know what they mean.

Regardless, the Tram upgrade bid included Air Conditioning. RIOC sought out proposals that included it and it was part of the winning bid. Then, once it was "too hard to do", it seems they dropped it without so much as a second thought.

It's not about complaining, it's about expecting a newly renovated and modernized transportation option to have something that should and could be present. Even the old subway cars had fans in them.

The Tram is - like it or not - one of the more unique things about our island. It attracts visitors and also serves all residents. Asking for it to be comfortable and convenient doesn't seem like a silly request.
Another resident:
Its not about not being able to deal with the heat. Its the fact that RIOC isn't solving simple problems, and in the case of the tram station remodel making things hotter, more cramped, and less enjoyable. How much did they spend on "updating" the perfectly good tram station so now that place sizzles like a green house? This problem is so easily solved it is laughable that it hasn't been yet.
and:
The tram upgrade was not completed according to the contract. There was also a daily monetary penalty for not finishing on time, which I don't think was ever collected or deducted from the cost. In the real world they would have been sued by the other bidder or bidders and probably RIOC. I would suspect that the former management of RIOC thought that they could do whatever they wanted, tell people anything and then duck the problem.

Saturday, July 21, 2012

Roosevelt Island Tram Station and Tram Cabin Overcrowding Today- Only 1 Tram Cabin Operating Today And No F Train Subway Service To Manhattan From Roosevelt Island

 Roosevelt Island Tram Station Crowding today

Reported yesterday on the lack of Manhattan bound F Train subway service from Roosevelt Island this weekend and previous meeting of Roosevelt Island Operating Corp (RIOC) Operations Committee meeting in which the RIOC Directors complained to RIOC staff when only one Tram Cabin was operating during previous F train subway service disruptions.

It happened again today that only one Tram cabin was operating when there was no F train service from Roosevelt Island to Manhattan. One resident reported this morning:
The tram station is so packed that I had to wait for the next tram due to overcrowding. I am now running late for work and very irritated; all as the other tram car sits idly behind me. I don't get the point of having two trams if only one will be in use. When are we going to get some better management for this thing???
When I arrived at the Roosevelt Island Tram Station this afternoon, the area was jam packed with people waiting for the Tram. Only one cabin was in operation because there was a problem with a gear on the South Tower. I was told that as soon as the Tram Tower problem was fixed, both cabins would be running.

Here's what happened while waiting at the Tram Station this afternoon



and then boarding the one working Tram Cabin. The Tram Cabin was so overcrowded that several people were asked to get off and wait for the next Tram. The Cabin Operator made the best of a bad situation and did his job very well.

Monday, September 26, 2011

Roosevelt Island Tram South Cabin Operating At Half Capacity Advises RIOC - What Does That Mean?

Received the following advisory from Roosevelt Island Operating Corp (RIOC):

Please be advised that the South Tram cabin will be operating at a 50% capacity until further notice.

Sincerely,

Roosevelt Island Operating Corp Advisories Group
I've asked RIOC for further explanation and will update when answer received.

Monday, August 8, 2011

Roosevelt Island Tram Cabin Gets Stuck After Leaving Tram Station This Morning - Can't Move Forward To Manhattan and After 10 Minutes Is Hauled Back To Roosevelt Island Tram Station

Received this message from a Roosevelt Island resident who was stuck briefly on the Roosevelt Island Tram this morning:

Was on the north cabin 7:15 am tram this am,  shortly as we started our trip the cabin stopped moving.  We didn’t even make it as far as the visitor’s kiosk.  Sat there about 10 minutes,  they were unable to get us to move forward.  We finally got hauled  back to the station,  and the south cabin then took us across.

Those cabins sure do get HOT when you are not moving!
I asked RIOC for comment as to what happened with the Tram this morning but have not heard back at the time this is published. Will update if RIOC responds with an explanation.

In the event that a stuck Roosevelt Island Tram cabin is not able to make it back to one of the Stations, here's how Tram Riders may get rescued by the New York City Fire Department.


You Tube Video of FDNY Roosevelt Island Tram Rescue Drill

That first step out of the Cabin is a doozy.

Thursday, July 28, 2011

Recent Heat Wave Strains Roosevelt Island Tram Motors - Cabins Operated At Reduced Capacity Due To Extremely Hot Temperatures In Mechanical Room

 Image of Extreme Heat From Houston Style

On July 19 the Roosevelt Island Operating Corp (RIOC) issued this Tram advisory:
Please be advised the South Tram Cabin is running at a reduced capacity until further notice.
On July 22 RIOC issued this advisory:
Please be advised the South Tram Cabin is running at a reduced capacity until further notice.
On July 26 RIOC issued this advisory
The South Cabin is temporary out of service. The north Cabin is unaffected .
I inquired of Roosevelt Island Operating Corp (RIOC) Vice President of Operations Fernando Martinez:
The South Tram Cabin has been experiencing difficulty recently with several service advisories issues regarding disruption in service.

What is the problem?
Mr. Martinez replied:
During the recent heat wave, the mechanical rooms became extremely hot.  We ran the Tram at reduced capacity in order not to over work the motors.  The disruption of service on the South Tram was due to a part failure.  The part was immediately replaced and tested, and the Tram was returned to service.

Thursday, July 14, 2011

Only One Roosevelt Island Tram Cabin Operating During This Afternoon/Evening Rush Hour As RIOC Is Performing Maintenance On Other Cabin

Just received this advisory from the Roosevelt Island Operating Corp (RIOC):

Please be advised during today's rush hour schedule, maintenance will be performed on one Tram cabin. Please allow for extra travel time as there may be slight delays.

Saturday, February 19, 2011

Roosevelt Island Tram Service Interruptions Earlier This Week - Here's Why, Kinks Still Being Worked Out On New Tram System

 Image Of Tram Control Room From Remontees-Mecaniques

Earlier this week, the Roosevelt Island Tram experienced brief interruptions in service. Roosevelt Island Operating Corp. (RIOC) Vice President Of Operations Fernando Martinez explains what happened:
Earlier this week, two minor malfunctions caused a disruption in Tram service.In both cases, RIOC was able to quickly identify the problem, make repairs, and return the Tram to full operation. As with any transportation system, especially a new one, minor disruptions to service are expected. RIOC will continue to identify way to reduce disruptions, while putting public safety first.

The two specific incidents include:

1. On Sunday, February 13th. at 2:48 A.M., the Ethernet link communication system lost power and communication between the control room and the cabins was interrupted. The unit was replaced and the tram resumed operation at 7:05 A.M.

2. On Monday, February 14th. at 7:48 A.M., the South Tram’s monitoring system receiver antenna’s supporting bracket ruptured,resulting in a signal loss. Repairs were completed and the tram was returned to operation by 10:15 A.M.